K-4 - Professional Services Agreement - Highway 6 Reconstruction - MSA
Page 11 of 13
Text read by the vision model; check the PDF for anything that matters.PROJECT SCHEDULE
<table>
<tr>
<th>TASK</th>
<th>START</th>
<th>END</th>
</tr>
<tr>
<td>D05 - Plans to Right Of Way</td>
<td>7/22/2024</td>
<td>10/4/2024</td>
</tr>
<tr>
<td>P09 - Public Information Meeting (PIM)</td>
<td>3/5/2025</td>
<td>3/5/2025</td>
</tr>
<tr>
<td>DM5 - Design Methods Turn-In</td>
<td>6/30/2026</td>
<td>6/30/2026</td>
</tr>
<tr>
<td>D08 - Final Grade and Pave Plans</td>
<td>2/23/2026</td>
<td>8/4/2026</td>
</tr>
<tr>
<td>L03 - Letting-Combination Grade and Pave</td>
<td>10/20/2026</td>
<td>10/20/2026</td>
</tr>
</table>
PROJECT COST
<table>
<tr>
<th>PHASE</th>
<th>NAME</th>
<th>COST</th>
</tr>
<tr>
<td>100</td>
<td>Project Management & Admin</td>
<td>$34,000</td>
</tr>
<tr>
<td>250</td>
<td>Data Collection</td>
<td>$13,200</td>
</tr>
<tr>
<td>300</td>
<td>Utility Coordination</td>
<td>$33,800</td>
</tr>
<tr>
<td>400</td>
<td>Environmental, Agency Coordination, Permitting</td>
<td>$20,660</td>
</tr>
<tr>
<td>500</td>
<td>Concept Statement (30%)</td>
<td>$137,000</td>
</tr>
<tr>
<td>550</td>
<td>Right of Way</td>
<td>$24,000</td>
</tr>
<tr>
<td>600</td>
<td>Preliminary Design (60%)</td>
<td>$123,850</td>
</tr>
<tr>
<td>700</td>
<td>Public Involvement</td>
<td>$16,900</td>
</tr>
<tr>
<td>800</td>
<td>Final Design & Letting</td>
<td>$167,115</td>
</tr>
<tr>
<td>900</td>
<td>Meetings</td>
<td>$32,280</td>
</tr>
<tr>
<td colspan="2">TOTAL</td>
<td><b>$602,805</b></td>
</tr>
</table>
Sources
- sharepoint (K-4 - Professional Services Agreement - Highway 6 Reconstruction - MSA.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.