resolution · I-4
I-4 - Resolution 2024-051 - Award of Bid for Water Treatment Plant Upgrade - Electrical Equipment and Controls
Page 2 of 4
Text read by the vision model; check the PDF for anything that matters.August 1, 2024
Doug Boldt, City Administrator
300 Railroad Street
Tiffin, IA 52340
Re: Water Treatment Plant Upgrade – Electrical Equipment Procurement
City of Tiffin
Dear Mr. Boldt
Upon review of the bids received on July 30, 2024 for the above-referenced project, it was found that they were submitted by qualified contractors. It is our recommendation that the bid from the lowest responsive, responsible bidder listed below for each electrical equipment package be accepted at your next meeting.
EP1 – Standby Generator and ATS Procurement
Altorfer Power Systems
2550 6th Street SW
Cedar Rapids, IA 52404 Bid Amount $329,890.00
EP2 – Electrical Equipment and Controls Procurement
Automatic Systems Co.
2740 Ford Street
Ames, IA 50010 Bid Amount $1,172,339.00
Please execute one (1) copy of the Notice of Award for each contract and email me a signed copy. After receiving the executed copies, we will forward a copy of the Notice of Award to each vendor. The vendors will then send a detailed purchase order for the City to execute. The purchase order will eventually be transferred to the General Contractor for the WTP Upgrade.
Sincerely,
MSA Professional Services, Inc.
Clint Wienen, P.E.
Project Engineer
Enc.