Text from the PDF text layer; check the PDF for anything that matters. Exhibit 1 - Cost Summary
Tiffin Community Recreation Center
Building Excellence 5/6/2025
.
Section Description Details GMP
Data Cabling and Backbone Allowance $ 250,000
Access Control Allowance $ 34,000
CCTV Allowance $ 45,000
Landscaping Allowance $ 75,000
Unreleased Add. #3 - Separate Fire Line from Water Line Allowance $ 10,000
Subtotal $ 11,351,685
Insurance Requirements Included in Fee $ -
Builder's Risk Insurance Included in Fee $ -
Railroad Insurance Added Scope $ 5,050
Construction Manager's Contingency Allowance $ 567,585
Collaboration Software Included in Fee $ -
Subtotal $ 11,924,320
Special Site Permitting (Wells, Air, Environmental) N.I.C.
Geotechnical Investigation N.I.C.
Subtotal $ 11,924,320
Preconstruction Fee $ 10,000
Construction Fee 4.20% $ 500,821
Project Construction Subtotal $ 12,435,142
Performance and Payment Bond Included in Fee $ -
Construction Total $ 12,435,142
Design & Engineering Fees $ -
Unsuitable Soils $ -
Owner FFE $ -
Fitness Equipment $ -
Bleachers $ -
Flood Insurance Deductible Buydown Premium $ -
Project Total $ 12,435,142