Text from the PDF text layer; check the PDF for anything that matters. Exhibit 1-Cost Summary
Tiffin Community Recreation Center
Building Excellence 5/6/2025
.
Section Description Details GMP
Bid Package 1
13.00 Metal Building Systems Merit Construction Company $ 1,997,300
14.20 Elevators Otis Elevator Company $ 122,000
31.00 Earthwork Schrader Excavating & Grading $ 315,386
31.60 Aggregate Piers CNC Foundations $ 135,379
32.14 Asphalt Paving LL Pelling Company Inc $ 169,606
32.16 Site Concrete All American Concrete, Inc $ 82,800
33.00 Site Utilities Freeman Construction Inc $ 64,708
Bid Package 1 Subtotal $ 2,887,179
Bid Package 2
03.30 Cast In Place Concrete To be bid at a later date $ 813,985
04.00 Masonry To be bid at a later date $ 344,553
05.00 Steel Fabrication and Erection To be bid at a later date $ 987,710
06.00 General Trades To be bid at a later date $ 327,150
08.33 Rolling Doors and Shutters To be bid at a later date $ 6,890
08.40 Aluminum Windows, Entrances, Glass/Glazing To be bid at a later date $ 611,932
09.20 Gypsum Board Systems To be bid at a later date $ 320,909
09.30 Tile To be bid at a later date $ 13,129
09.50 Suspended Acoustical Ceilina and Acoustical Panels To be bid at a later date $ 117,427
09.64 Wood Athletic Flooring To be bid at a later date $ 240,000
09.65 Resilient Flooring, Base and Carpet To be bid at a later date $ 67,829
09.66 Resilient Athletic Floorina To be bid at a later date $ 269,255
09.90 Painting and Wallcovering To be bid at a later date $ 161,504
10.11 Building Signage To be bid at a later date $ 80,097
11.66 Athletic Equipment To be bid at a later date $ 300,600
21.00 Fire Suooression To be bid at a later date $ 204,120
22.00 Plumbing To be bid at a later date $ 383,200
23.00 HVAC To be bid at a later date $ 935,847
26.00 Electrical To be bid at a later date $ 823,355
32.18 Athletic Turf Surfacing To be bid at a later date $ 45,000
32.90 Segmented Retaining Wall Included in Allowance Below $ -
Bid Package 2 Subtotal $ 7,054,492
Direct Cost $ 9,941,671
General Conditions Lump Sum $ 503,136
General Requirements Allowance $ 206,878
Building Permit by Owner $ -
Testing & Inspections Allowance $ 40,000
New Utility Services Allowance $ 40,000
Mill and Overlay North Parking Lot Allowance $ 101,000
Flood Insurance Deductible Allowance $ 25,000
CMU Enhancements Allowance $ 35,000
Lobby Alternate Ceiling Allowance $ 45,000