contract agreement · K-7
K-7 - Guaranteed Maximum Price Amendment - Miron
Page 4 of 10
Text from the PDF text layer; check the PDF for anything that matters. Item Price
General Requirements $206,878
Testing & Inspections $40,000
New Utility Services $40,000
Mill & Overlay North Parking Lot $101,000
Flood Insurance Deductible $25,000
CMU Enhancements $35,000
Lobby Alternate Ceiling $45,000
Data Cabling and Backbone $250,000
Access Control $34,000
CCTV $45,000
Landscaping $75,000
Unreleased Add. #3- Fire Line $10,000
Construction Manager Contingency $567,585
§ A.3.1.6 Assumptions and clarifications, if any, upon which the Guaranteed Maximum Price is based:
(Identify each assumption and clarification.)
A. The following items are included as follows (clarifying drawing inconsistencies):
1. Flooring listed as SC on the room finish schedule on A2.6 Schedules is assumed to be grey sealed concrete
floors and no additional coloring, grinding or other finishes in the base price.
2. The interior CMU is assumed to be normal CMU with regular grout joints and painted. An upgrade to those
walls can be funded by the allowance for CMU Enhancements.
3. Tall storage cabinets in Studio 122 and 123.
4. Bench on the backside of counter between Lobby 102 and Courts 126.
5. ACT in lobby 102 and Corridor 117 (Upgrades to be determined and funded from Allowance.)
6. Full height wall tile on wet walls in restrooms.
7. Acoustic wall panels in Studio 122 & 123 and Turf Room I 25, totaling 570 square feet.
8. 2high segmented retaining wall.
9. Curtain wall is assumed for exterior glazing per subcontractor recommendation at this time.
B. The following items are excluded for the scope of this amendment.
1. Design and Engineering Fees.
2. Replacement of Unsuitable Soils contrary to Geotechnical Report.
3. Owner Furniture and Equipment.
4. Pickleball nets are assumed to be mobile and part ofFF&E.
5. Fitness Equipment.
6. Bleachers.
7. Scoreboards.
8. Decorative handrails and/or glass handrails.
9. Abuse-resistant drywall.
I 0. Re-striping of soccer fields.
11. Demolition, modifications, or relocation of existing tennis courts.
12. Building new or moving of park shelter.
13. Monument signs.
14. Relocation or demolition of existing exterior light poles.
15. Washer and dryer.
16. Foundation wall below CMU walls on WF3 footing.
17. Wall tile in locker rooms.
18. Flood Insurance Deductible Buydown Premium.
§ A.3.1.7 The Guaranteed Maximum Price is based upon the following other documents and information:
(List any other documents or information here, or refer to an exhibit attached to this Amendment.)
AIA Document A 133- 2019 Exhibit A. Copyright 1991, 2003, 2009, and 2019. All rights reserved. "The American Institute of Architects," "American Institute of
lnit. Architects," "AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 18:38:39
ET on 05/02/2025 under Order No.4104244063 which expires on 06/30/2025, is not for resale, is licensed for one-time use only, and may only be used in
4
accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail [email protected].
User Notes: (843918169)
Sources
- sharepoint (K-7 - Guaranteed Maximum Price Amendment - Miron.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.