Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
May 1, 2025
PROJECT UPDATE
NORTH PARK ROAD IMPROVEMENTS – JAMES WATTERS
MSA has submitted a professional services agreement for construction observation and administration for
the for the project. Construction started in late February with tree clearing work.
Clearing and grubbing in the creek area just south of Mopar Drive is complete and temporary seeding has
been placed. Construction of storm sewer and water main on the west side from south end of project to
just north of the elementary school bus loop have been installed. Televising of the installed storm sewer
has been completed and an assessment has been sent to Public Works staff.
The detour of N Park Rd for through traffic was placed on April 28th. MSA and City have been in coordination
with CCA schools who have issued newsletters to parents informing them of the upcoming detour route.
Following feedback on the function of the closure, additional signs have been added along Highway 6 to
indicate that North Park Road is closed.
The section of North Park Road from the school bus loop to the Oak Hill Elementary entrance has been
closed for Stage 1A. Excavation, placement of the pedestrian underpass, additional storm sewer and water
main are anticipated to begin in early May.
Stage 1B closures at Oak Hill’s entrance and the bus loop entrance will take place after classes are finished
for the summer and any additional staff days are determined. This is anticipated to be the first week of
June.
PROJECT UPDATE
Page 2 of 4