Text from the PDF text layer; check the PDF for anything that matters.§ 3.1.7 As the Architect progresses with the preparation of the Schematic Design, Design Development and
Construction Documents, the Construction Manager shall consult with the Owner and Architect and make
recommendations regarding constructability and schedules, for the Architect’s review and the Owner’s approval.
§ 3.1.8 The Construction Manager shall provide recommendations and information to the Owner and Architect
regarding equipment, materials, services, and temporary Project facilities.
§ 3.1.9 The Construction Manager shall provide a staffing plan for Preconstruction Phase services for the Owner’s
review and approval.
§ 3.1.10 If the Owner identified a Sustainable Objective in Article 1, the Construction Manager shall fulfill its
Preconstruction Phase responsibilities as required in AIA Document E234™–2019, Sustainable Projects Exhibit,
Construction Manager as Constructor Edition, attached to this Agreement.
§ 3.1.11 Subcontractors and Suppliers
§ 3.1.11.1 If the Owner has provided requirements for subcontractor procurement in section 1.1.14, the Construction
Manager shall provide a subcontracting plan, addressing the Owner’s requirements, for the Owner’s review and
approval.
§ 3.1.11.2 The Construction Manager shall develop bidders’ interest in the Project.
§ 3.1.11.3 The processes described in Article 9 shall apply if bid packages will be issued during the Preconstruction
Phase.
§ 3.1.12 Procurement
The Construction Manager shall prepare, for the Architect’s review and the Owner’s acceptance, a procurement
schedule for items that must be ordered in advance of construction. The Construction Manager shall expedite and
coordinate the ordering and delivery of materials that must be ordered in advance of construction. If the Owner
agrees to procure any items prior to the establishment of the Guaranteed Maximum Price, the Owner shall procure
the items on terms and conditions acceptable to the Construction Manager. Upon the establishment of the
Guaranteed Maximum Price, the Owner shall assign all contracts for these items to the Construction Manager and
the Construction Manager shall thereafter accept responsibility for them.
§ 3.1.13 Compliance with Laws
The Construction Manager shall comply with applicable laws, statutes, ordinances, codes, rules and regulations, and
lawful orders of public authorities applicable to its performance under this Contract, and with equal employment
opportunity programs, and other programs as may be required by governmental and quasi-governmental authorities.
§ 3.1.14 Other Preconstruction Services
Insert a description of any other Preconstruction Phase services to be provided by the Construction Manager, or
reference an exhibit attached to this document
(Describe any other Preconstruction Phase services, such as providing cash flow projections, development of a
project information management system, early selection or procurement of subcontractors, etc.)
« »
§ 3.2 Guaranteed Maximum Price Proposal
§ 3.2.1 At a time to be mutually agreed upon by the Owner and the Construction Manager, the Construction Manager
shall prepare a Guaranteed Maximum Price proposal for the Owner’s and Architect’s review, and the Owner’s
acceptance. The Guaranteed Maximum Price in the proposal shall be the sum of the Construction Manager’s
estimate of the Cost of the Work, the Construction Manager’s contingency described in Section 3.2.4, and the
Construction Manager’s Fee described in Section 6.1.2.
§ 3.2.2 To the extent that the Contract Documents are anticipated to require further development, the Guaranteed
Maximum Price includes the costs attributable to such further development consistent with the Contract Documents
and reasonably inferable therefrom. Such further development does not include changes in scope, systems, kinds and
quality of materials, finishes, or equipment, all of which, if required, shall be incorporated by Change Order.
AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American
Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This
draft was produced at 10:57:51 ET on 09/18/2024 under Order No.4104244063 which expires on 01/20/2025, is not for resale, is licensed for 7
one-time use only, and may only be used in accordance with the AIA Contract Documents ® Terms of Service. To report copyright violations, e-
mail [email protected].
User Notes: (3B9ADA45)