contract agreement · J-1
J-1 - Miron Contract - Recreation Center - A133
Page 8 of 24
Text from the PDF text layer; check the PDF for anything that matters.§ 3.2.3 The Construction Manager shall include with the Guaranteed Maximum Price proposal a written statement of
its basis, which shall include the following:
.1 A list of the Drawings and Specifications, including all Addenda thereto, and the Conditions of the
Contract;
.2 A list of the clarifications and assumptions made by the Construction Manager in the preparation of the
Guaranteed Maximum Price proposal, including assumptions under Section 3.2.2;
.3 A statement of the proposed Guaranteed Maximum Price, including a statement of the estimated Cost
of the Work organized by trade categories or systems, including allowances; the Construction
Manager’s contingency set forth in Section 3.2.4; and the Construction Manager’s Fee;
.4 The anticipated date of Substantial Completion upon which the proposed Guaranteed Maximum Price
is based; and
.5 A date by which the Owner must accept the Guaranteed Maximum Price.
§ 3.2.4 In preparing the Construction Manager’s Guaranteed Maximum Price proposal, the Construction Manager
shall include a contingency for the Construction Manager’s exclusive use to cover those costs that are included in
the Guaranteed Maximum Price but not otherwise allocated to another line item or included in a Change Order.
§ 3.2.5 The Construction Manager shall meet with the Owner and Architect to review the Guaranteed Maximum
Price proposal. In the event that the Owner or Architect discover any inconsistencies or inaccuracies in the
information presented, they shall promptly notify the Construction Manager, who shall make appropriate
adjustments to the Guaranteed Maximum Price proposal, its basis, or both.
§ 3.2.6 If the Owner notifies the Construction Manager that the Owner has accepted the Guaranteed Maximum Price
proposal in writing before the date specified in the Guaranteed Maximum Price proposal, the Guaranteed Maximum
Price proposal shall be deemed effective without further acceptance from the Construction Manager. Following
acceptance of a Guaranteed Maximum Price, the Owner and Construction Manager shall execute the Guaranteed
Maximum Price Amendment amending this Agreement, a copy of which the Owner shall provide to the Architect.
The Guaranteed Maximum Price Amendment shall set forth the agreed upon Guaranteed Maximum Price with the
information and assumptions upon which it is based.
§ 3.2.7 The Construction Manager shall not incur any cost to be reimbursed as part of the Cost of the Work prior to
the execution of the Guaranteed Maximum Price Amendment, unless the Owner provides prior written authorization
for such costs.
§ 3.2.8 The Owner shall authorize preparation of revisions to the Contract Documents that incorporate the agreed-
upon assumptions and clarifications contained in the Guaranteed Maximum Price Amendment. The Owner shall
promptly furnish such revised Contract Documents to the Construction Manager. The Construction Manager shall
notify the Owner and Architect of any inconsistencies between the agreed-upon assumptions and clarifications
contained in the Guaranteed Maximum Price Amendment and the revised Contract Documents.
§ 3.2.9 The Construction Manager shall include in the Guaranteed Maximum Price all sales, consumer, use and
similar taxes for the Work provided by the Construction Manager that are legally enacted, whether or not yet
effective, at the time the Guaranteed Maximum Price Amendment is executed.
§ 3.3 Construction Phase
§ 3.3.1 General
§ 3.3.1.1 For purposes of Section 8.1.2 of A201–2017, the date of commencement of the Work shall mean the date of
commencement of the Construction Phase.
§ 3.3.1.2 The Construction Phase shall commence upon the Owner’s execution of the Guaranteed Maximum Price
Amendment or, prior to acceptance of the Guaranteed Maximum Price proposal, by written agreement of the parties.
The written agreement shall set forth a description of the Work to be performed by the Construction Manager, and
any insurance and bond requirements for Work performed prior to execution of the Guaranteed Maximum Price
Amendment.
AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American
Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This
draft was produced at 10:57:51 ET on 09/18/2024 under Order No.4104244063 which expires on 01/20/2025, is not for resale, is licensed for 8
one-time use only, and may only be used in accordance with the AIA Contract Documents ® Terms of Service. To report copyright violations, e-
mail [email protected].
User Notes: (3B9ADA45)
Sources
- sharepoint (J-1 - Miron Contract - Recreation Center - A133.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.