contract agreement · J-1
J-1 - Miron Contract - Recreation Center - A133
Page 5 of 24
Text from the PDF text layer; check the PDF for anything that matters.§ 1.3 Neither the Owner’s nor the Construction Manager’s representative shall be changed without ten days’ prior
notice to the other party.
ARTICLE 2 GENERAL PROVISIONS
§ 2.1 The Contract Documents
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other
Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed
in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract and
are as fully a part of the Contract as if attached to this Agreement or repeated herein. Upon the Owner’s acceptance
of the Construction Manager’s Guaranteed Maximum Price proposal, the Contract Documents will also include the
documents described in Section 3.2.3 and identified in the Guaranteed Maximum Price Amendment and revisions
prepared by the Architect and furnished by the Owner as described in Section 3.2.8. The Contract represents the
entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or
agreements, either written or oral. If anything in the other Contract Documents, other than a Modification, is
inconsistent with this Agreement, this Agreement shall govern. An enumeration of the Contract Documents, other
than a Modification, appears in Article 15.
§ 2.2 Relationship of the Parties
The Construction Manager accepts the relationship of trust and confidence established by this Agreement and
covenants with the Owner to cooperate with the Architect and exercise the Construction Manager’s skill and
judgment in furthering the interests of the Owner to furnish efficient construction administration, management
services, and supervision; to furnish at all times an adequate supply of workers and materials; and to perform the
Work in an expeditious and economical manner consistent with the Owner’s interests. The Owner agrees to furnish
or approve, in a timely manner, information required by the Construction Manager and to make payments to the
Construction Manager in accordance with the requirements of the Contract Documents.
§ 2.3 General Conditions
§ 2.3.1 For the Preconstruction Phase, AIA Document A201™–2017, General Conditions of the Contract for
Construction, shall apply as follows: Section 1.5, Ownership and Use of Documents; Section 1.7, Digital Data Use
and Transmission; Section 1.8, Building Information Model Use and Reliance; Section 2.2.4, Confidential
Information; Section 3.12.10, Professional Services; Section 10.3, Hazardous Materials; Section 13.1, Governing
Law. The term “Contractor” as used in A201–2017 shall mean the Construction Manager.
§ 2.3.2 For the Construction Phase, the general conditions of the contract shall be as set forth in A201–2017, which
document is incorporated herein by reference. The term “Contractor” as used in A201–2017 shall mean the
Construction Manager.
ARTICLE 3 CONSTRUCTION MANAGER’S RESPONSIBILITIES
The Construction Manager’s Preconstruction Phase responsibilities are set forth in Sections 3.1 and 3.2, and in the
applicable provisions of A201-2017 referenced in Section 2.3.1. The Construction Manager’s Construction Phase
responsibilities are set forth in Section 3.3. The Owner and Construction Manager may agree, in consultation with
the Architect, for the Construction Phase to commence prior to completion of the Preconstruction Phase, in which
case, both phases will proceed concurrently. The Construction Manager shall identify a representative authorized to
act on behalf of the Construction Manager with respect to the Project.
§ 3.1 Preconstruction Phase
§ 3.1.1 Extent of Responsibility
The Construction Manager shall exercise reasonable care in performing its Preconstruction Services. The Owner and
Architect shall be entitled to rely on, and shall not be responsible for, the accuracy, completeness, and timeliness of
services and information furnished by the Construction Manager. The Construction Manager, however, does not
warrant or guarantee estimates and schedules except as may be included as part of the Guaranteed Maximum Price.
The Construction Manager is not required to ascertain that the Drawings and Specifications are in accordance with
applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, but the
Construction Manager shall promptly report to the Architect and Owner any nonconformity discovered by or made
known to the Construction Manager as a request for information in such form as the Architect may require.
§ 3.1.2 The Construction Manager shall provide a preliminary evaluation of the Owner’s program, schedule and
construction budget requirements, each in terms of the other.
AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American
Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This
draft was produced at 10:57:51 ET on 09/18/2024 under Order No.4104244063 which expires on 01/20/2025, is not for resale, is licensed for 5
one-time use only, and may only be used in accordance with the AIA Contract Documents ® Terms of Service. To report copyright violations, e-
mail [email protected].
User Notes: (3B9ADA45)