J-1 - Miron Contract - Recreation Center - A133
Page 18 of 24
Text from the PDF text layer; check the PDF for anything that matters. .4 For Work performed or defects discovered since the last payment application, any amount for which
the Architect may withhold payment, or nullify a Certificate of Payment in whole or in part, as
provided in Article 9 of AIA Document A201–2017;
.5 The shortfall, if any, indicated by the Construction Manager in the documentation required by Section
11.1.4 to substantiate prior Applications for Payment, or resulting from errors subsequently
discovered by the Owner’s auditors in such documentation; and
.6 Retainage withheld pursuant to Section 11.1.8.
§ 11.1.8 Retainage
§ 11.1.8.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold
the following amount, as retainage, from the payment otherwise due:
(Insert a percentage or amount to be withheld as retainage from each Application for Payment. The amount of
retainage may be limited by governing law.)
«Retainage of five percent (5%) will be applicable. »
§ 11.1.8.1.1 The following items are not subject to retainage:
(Insert any items not subject to the withholding of retainage, such as general conditions, insurance, etc.)
§ 11.1.8.2 Reduction or limitation of retainage, if any, shall be as follows:
(If the retainage established in Section 11.1.8.1 is to be modified prior to Substantial Completion of the entire Work,
insert provisions for such modification.)
None
§ 11.1.8.3 Except as set forth in this Section 11.1.8.3, upon Substantial Completion of the Work, the Construction
Manager may submit an Application for Payment that includes the retainage withheld from prior Applications for
Payment pursuant to this Section 11.1.8. The Application for Payment submitted at Substantial Completion shall not
include retainage as follows:
(Insert any other conditions for release of retainage, such as upon completion of the Owner’s audit and
reconciliation, upon Substantial Completion.)
«»
§ 11.1.9 If final completion of the Work is materially delayed through no fault of the Construction Manager, the
Owner shall pay the Construction Manager any additional amounts in accordance with Article 9 of AIA Document
A201–2017.
§ 11.1.10 Except with the Owner’s prior written approval, the Construction Manager shall not make advance
payments to suppliers for materials or equipment which have not been delivered and suitably stored at the site.
§ 11.1.11 The Owner and the Construction Manager shall agree upon a mutually acceptable procedure for review and
approval of payments to Subcontractors, and the percentage of retainage held on Subcontracts, and the Construction
Manager shall execute subcontracts in accordance with those agreements.
§ 11.1.12 In taking action on the Construction Manager’s Applications for Payment the Architect shall be entitled to
rely on the accuracy and completeness of the information furnished by the Construction Manager, and such action
shall not be deemed to be a representation that (1) the Architect has made a detailed examination, audit, or
arithmetic verification, of the documentation submitted in accordance with Section 11.1.4 or other supporting data;
(2) that the Architect has made exhaustive or continuous on-site inspections; or (3) that the Architect has made
examinations to ascertain how or for what purposes the Construction Manager has used amounts previously paid on
account of the Contract. Such examinations, audits, and verifications, if required by the Owner, will be performed
by the Owner’s auditors acting in the sole interest of the Owner.
§ 11.2 Final Payment
§ 11.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to
the Construction Manager when
AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American
Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This
draft was produced at 10:57:51 ET on 09/18/2024 under Order No.4104244063 which expires on 01/20/2025, is not for resale, is licensed for 18
one-time use only, and may only be used in accordance with the AIA Contract Documents ® Terms of Service. To report copyright violations, e-
mail [email protected].
User Notes: (3B9ADA45)
Sources
- sharepoint (J-1 - Miron Contract - Recreation Center - A133.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.