Text from the PDF text layer; check the PDF for anything that matters.§ 11.1.4 With each Application for Payment, the Construction Manager shall submit payrolls, petty cash accounts,
receipted invoices or invoices with check vouchers attached, and any other evidence required by the Owner or
Architect to demonstrate that payments already made by the Construction Manager on account of the Cost of the
Work equal or exceed progress payments already received by the Construction Manager, plus payrolls for the period
covered by the present Application for Payment, less that portion of the progress payments attributable to the
Construction Manager’s Fee.
§ 11.1.5 Each Application for Payment shall be based on the most recent schedule of values submitted by the
Construction Manager in accordance with the Contract Documents. The schedule of values shall allocate the entire
Guaranteed Maximum Price among: (1) the various portions of the Work; (2) any contingency for costs that are
included in the Guaranteed Maximum Price but not otherwise allocated to another line item or included in a Change
Order; and (3) the Construction Manager’s Fee.
§ 11.1.5.1 The schedule of values shall be prepared in such form and supported by such data to substantiate its
accuracy as the Architect may require. The schedule of values shall be used as a basis for reviewing the
Construction Manager’s Applications for Payment.
§ 11.1.5.2 The allocation of the Guaranteed Maximum Price under this Section 11.1.5 shall not constitute a separate
guaranteed maximum price for the Cost of the Work of each individual line item in the schedule of values.
§ 11.1.5.3 When the Construction Manager allocates costs from a contingency to another line item in the schedule of
values, the Construction Manager shall submit supporting documentation to the Architect.
§ 11.1.6 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end
of the period covered by the Application for Payment. The percentage of completion shall be the lesser of (1) the
percentage of that portion of the Work which has actually been completed, or (2) the percentage obtained by
dividing (a) the expense that has actually been incurred by the Construction Manager on account of that portion of
the Work and for which the Construction Manager has made payment or intends to make payment prior to the next
Application for Payment, by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in
the schedule of values.
§ 11.1.7 In accordance with AIA Document A201–2017 and subject to other provisions of the Contract Documents,
the amount of each progress payment shall be computed as follows:
§ 11.1.7.1 The amount of each progress payment shall first include:
.1 That portion of the Guaranteed Maximum Price properly allocable to completed Work as determined
by multiplying the percentage of completion of each portion of the Work by the share of the
Guaranteed Maximum Price allocated to that portion of the Work in the most recent schedule of
values;
.2 That portion of the Guaranteed Maximum Price properly allocable to materials and equipment
delivered and suitably stored at the site for subsequent incorporation in the completed construction or,
if approved in writing in advance by the Owner, suitably stored off the site at a location agreed upon
in writing;
.3 That portion of Construction Change Directives that the Architect determines, in the Architect’s
professional judgment, to be reasonably justified; and
.4 The Construction Manager’s Fee, computed upon the Cost of the Work described in the preceding
Sections 11.1.7.1.1 and 11.1.7.1.2 at the rate stated in Section 6.1.2 or, if the Construction Manager’s
Fee is stated as a fixed sum in that Section, an amount that bears the same ratio to that fixed-sum fee
as the Cost of the Work included in Sections 11.1.7.1.1 and 11.1.7.1.2 bears to a reasonable estimate
of the probable Cost of the Work upon its completion.
§ 11.1.7.2 The amount of each progress payment shall then be reduced by:
.1 The aggregate of any amounts previously paid by the Owner;
.2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously
withheld a Certificate for Payment as provided in Article 9 of AIA Document A201–2017;
.3 Any amount for which the Construction Manager does not intend to pay a Subcontractor or material
supplier, unless the Work has been performed by others the Construction Manager intends to pay;
AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American
Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This
draft was produced at 10:57:51 ET on 09/18/2024 under Order No.4104244063 which expires on 01/20/2025, is not for resale, is licensed for 17
one-time use only, and may only be used in accordance with the AIA Contract Documents ® Terms of Service. To report copyright violations, e-
mail [email protected].
User Notes: (3B9ADA45)