contract agreement · J-1
J-1 - Miron Contract - Recreation Center - A133
Page 19 of 24
Text from the PDF text layer; check the PDF for anything that matters. .1 the Construction Manager has fully performed the Contract, except for the Construction Manager’s
responsibility to correct Work as provided in Article 12 of AIA Document A201–2017, and to satisfy
other requirements, if any, which extend beyond final payment;
.2 the Construction Manager has submitted a final accounting for the Cost of the Work and a final
Application for Payment; and
.3 a final Certificate for Payment has been issued by the Architect in accordance with Section 11.2.2.2.
§ 11.2.2 Within 30 days of the Owner’s receipt of the Construction Manager’s final accounting for the Cost of the
Work, the Owner shall conduct an audit of the Cost of the Work or notify the Architect that it will not conduct an
audit.
§ 11.2.2.1 If the Owner conducts an audit of the Cost of the Work, the Owner shall, within 10 days after completion
of the audit, submit a written report based upon the auditors’ findings to the Architect.
§ 11.2.2.2 Within seven days after receipt of the written report described in Section 11.2.2.1, or receipt of notice that
the Owner will not conduct an audit, and provided that the other conditions of Section 11.2.1 have been met, the
Architect will either issue to the Owner a final Certificate for Payment with a copy to the Construction Manager, or
notify the Construction Manager and Owner in writing of the Architect’s reasons for withholding a certificate as
provided in Article 9 of AIA Document A201–2017. The time periods stated in this Section 11.2.2 supersede those
stated in Article 9 of AIA Document A201–2017. The Architect is not responsible for verifying the accuracy of the
Construction Manager’s final accounting.
§ 11.2.2.3 If the Owner’s auditors’ report concludes that the Cost of the Work, as substantiated by the Construction
Manager’s final accounting, is less than claimed by the Construction Manager, the Construction Manager shall be
entitled to request mediation of the disputed amount without seeking an initial decision pursuant to Article 15 of
AIA Document A201–2017. A request for mediation shall be made by the Construction Manager within 30 days
after the Construction Manager’s receipt of a copy of the Architect’s final Certificate for Payment. Failure to request
mediation within this 30-day period shall result in the substantiated amount reported by the Owner’s auditors
becoming binding on the Construction Manager. Pending a final resolution of the disputed amount, the Owner shall
pay the Construction Manager the amount certified in the Architect’s final Certificate for Payment.
§ 11.2.3 The Owner’s final payment to the Construction Manager shall be made no later than 30 days after the
issuance of the Architect’s final Certificate for Payment, or as follows:
«»
§ 11.2.4 If, subsequent to final payment, and at the Owner’s request, the Construction Manager incurs costs,
described in Sections 7.1 through 7.7, and not excluded by Section 7.9, to correct defective or nonconforming Work,
the Owner shall reimburse the Construction Manager for such costs, and the Construction Manager’s Fee applicable
thereto, on the same basis as if such costs had been incurred prior to final payment, but not in excess of the
Guaranteed Maximum Price. If adjustments to the Contract Sum are provided for in Section 6.1.7, the amount of
those adjustments shall be recalculated, taking into account any reimbursements made pursuant to this Section
11.2.4 in determining the net amount to be paid by the Owner to the Construction Manager.
§ 11.3 Interest
Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated
below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is
located.
(Insert rate of interest agreed upon, if any.)
0 % «per annum»
ARTICLE 12 DISPUTE RESOLUTION
§ 12.1 Initial Decision Maker
§ 12.1.1 Any Claim between the Owner and Construction Manager shall be resolved in accordance with the
provisions set forth in this Article 12 and Article 15 of A201–2017. However, for Claims arising from or relating to
the Construction Manager’s Preconstruction Phase services, no decision by the Initial Decision Maker shall be
AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American
Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This
draft was produced at 10:57:51 ET on 09/18/2024 under Order No.4104244063 which expires on 01/20/2025, is not for resale, is licensed for 19
one-time use only, and may only be used in accordance with the AIA Contract Documents ® Terms of Service. To report copyright violations, e-
mail [email protected].
User Notes: (3B9ADA45)
Sources
- sharepoint (J-1 - Miron Contract - Recreation Center - A133.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.