AGENDA ITEM # E-5 The request indicates no additional contract time was required for this work Staff Recommendation Staff recommends approval of Change Order No. 11 with Rathje Construction Co. in the amount of $14,040.00, increasing the contract price to $2,346,925.13 and providing a one-day extension of the contract completion date. ATTACHMENTS: Change Order 2