Approval of Change Order #11 – Rathje Construction Co. – Original Town Urbanization – Phase 3 — E-5
Page 2 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-5
The request indicates no additional contract time was required for this work
Staff Recommendation
Staff recommends approval of Change Order No. 11 with Rathje Construction Co. in the amount
of $14,040.00, increasing the contract price to $2,346,925.13 and providing a one-day extension
of the contract completion date.
ATTACHMENTS: Change Order