Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-5
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE:
October 1, 2026
AGENDA ITEM: Approval of Change Order #11 – Rathje Construction Co. – Original Town
Urbanization – Phase 3
ACTION: Motion
Background
The City of Tiffin contracted with Rathje Construction Co. for the Original Town Urbanization –
Phase 3 project. Change Order No. 11 is dated July 23, 2026, and addresses two field conditions
encountered during construction. The work associated with these items was performed after
verbal approval from the City.
The change order combines two previously submitted change order requests involving water
service sizing and additional frost protection for a shallow water main.
Change Order Items:
Additional Frost Protection – $12,240
During construction, it was discovered that the water main at the intersection of Third Street and
Grant Street was only approximately 3.5 feet below the paving elevation, providing insufficient
frost protection.
The project required additional protection to address the shallow water main. Rathje
Construction installed 6-inch rigid foam board insulation over approximately 720 square feet at a
unit price of $17.00 per square foot.
The total cost associated with this work is $12,240.00. The change order request indicates that
the work required one additional working day.
Water Service Size Modifications – $1,800
During water main installation, it was discovered that two existing water services—one serving
320 Main Street (Car Wash) and one serving 107 W. Marion Road (Bryant's Restaurant)—were
actually 2-inch services rather than the 1-inch size shown in the project plans.
To maintain the appropriate service size, the two services were replaced with 2-inch water
service corporations.
The change resulted in:
• Two 2-inch water service corporations: $2,700.00
• Credit for two 1-inch water service corporations: ($900.00)
• Net increase: $1,800.00
1
Sources
- revize: E-5 (e1QjpiNg6YFYhjZqDVF5EGSV4IR1fv.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-5 Approval of Change Order #11 – Rathje Construction Co. – Original Town Urbanization – Phase 3
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.