Approval of Change Order #11 – Rathje Construction Co. – Original Town Urbanization – Phase 3 — E-5
Page 3 of 5
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 7/23/2026
Change Order No: 11 (ELEVEN)
Agreement Date: 12/14/2023
PROJECT: Original Town Urbanization – Phase 3 HFC #18218.131
OWNER: Tiffin, IA
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Corporation stops for water services on U.S HWY 6 were found to be 2-inch instead of 1-inch per City records. Watermain in the intersection was found to be shallow and frost protections was requested by City staff. Both change order requests are dated in the fall of 2025 and the work was performed after verbal approval from the City.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $2,134,856.90
CONTRACT with LAST CHANGE ORDER: $2,332,885.13
THIS CHANGE ORDER AMOUNT: $14,040.00
NEW CONTRACT PRICE: $2,346,925.13
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 1 Day
NEW Completion Date: October 7, 2025
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See attached.
ENGINEER: ________________________________
Sources
- revize: E-5 (e1QjpiNg6YFYhjZqDVF5EGSV4IR1fv.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-5 Approval of Change Order #11 – Rathje Construction Co. – Original Town Urbanization – Phase 3
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.