Text read by the vision model; check the PDF for anything that matters.Certificate of Substantial Completion
Project:
Kimberlite Street – South Improvements Project
Owner:
City of Tiffin
Contract:
City of Tiffin – Kimberlite Street – South Improvements Project
Owner's Contract No.: ____________________________
Engineer's Project No.: 13603011
This definitive Certificate of Substantial Completion applies to:
☒ All Work under the Contract Documents. ☐ The following specified portions of the Work:
6/7/24
Date of Substantial Completion
The Work to which this Certificate applies has been inspected by authorized representatives of Owner, Contractor, and Engineer, and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby declared and is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below.
A definitive list of items to be completed or corrected is attached hereto. This list may not be all-inclusive, and the failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.
The responsibilities between Owner and Contractor for security, operation, safety, maintenance, heat, utilities, insurance and warranties shall be as provided in the Contract Documents except as amended as follows:
☒ Amended Responsibilities
☐ Not Amended
Owner's Amended Responsibilities:
None
Contractor's Amended Responsibilities:
See Attached
This Certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor is it a release of Contractor's obligation to complete the Work in accordance with the Contract Documents.
[Signature]
Executed by Engineer
06/13/2024
Date
Accepted by Contractor
Date
Accepted by Owner
Date