M-8 - City Engineer Report
Page 3 of 3
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
June 26, 2024
PROJECT UPDATE
Upcoming Infrastructure Description Next Steps/Schedule
Project
The current wastewater treatment facility (WWTF) has a chloride Final Compliance with NPDES
compliance schedule. There is not any wastewater treatment Permit required October 1, 2025.
equipment/processes designed to remove chloride so typically
source control is the only economical means of meeting MSA presented its findings on
Wastewater Treatment
compliance. The existing treatment facility is at about 50% November 1st, 2022. MSA has
Improvements
capacity. However, if the past growth rate continues an expansion prepared a proposed schedule
will be required in the next 5-7 years. for wastewater treatment, water
treatment and water supply
From design to construction the process typically takes 3-4 years. improvement projects.
MSA is preparing a proposal to model the existing sanitary sewer Proposal for modeling services
Systemwide sanitary sewer model system of Tiffin. This will assist in future review of developments to to be created and presented to
determine if existing system has necessary capacity for service. City.
DOT has requested concurrence from the City on permanent
improvements to intersection within 5 years of installation of
Discuss extension with DOT and
Deer View Ave & Tall Grass Ave & temporary traffic signals in 2020. Scope includes both pedestrian
begin conceptual review of
Hwy 6 Intersection Improvements and vehicle accommodations. MSA is reaching out to the DOT to
intersection/signals.
request a time extension and will begin conceptually reviewing the
signals and intersection for DOT approval.
PROJECT UPDATE
Page 3 of 3