K-3 - Pay Estimate 2 - Vieth Construction - Trail Phase 6 - Final
Page 2 of 3
Text read by the vision model; check the PDF for anything that matters.PARTIAL PAYMENT ESTIMATE NUMBER 2-FINAL
CONTRACTOR: Vieth Construction Corp.
ADDRESS: 6419 Nordic Dr.
CITY, STATE, ZIP Cedar Falls la 50613
OWNER: City of Tiffin
PROJECT: Trail Phase 6 Project
HFC#16218.200
<table>
<tr>
<th>Date of Completion:</th>
<th>Amount of Contract:</th>
<th>Date of Estimate:</th>
</tr>
<tr>
<td>Original: 9/30/2021</td>
<td>Original: $ 89,588.50</td>
<td>From: 1-Oct-21</td>
</tr>
<tr>
<td>Revised: 10/1/2021</td>
<td>Revised: $ 88,635.76 (C.O. #2)</td>
<td>To: 1-Sep-22</td>
</tr>
</table>
<table>
<tr>
<th></th>
<th>THIS PERIOD</th>
<th>TOTAL TO DATE</th>
</tr>
<tr>
<td>Amount Earned</td>
<td>$0.00</td>
<td>$ 84,739.10</td>
</tr>
<tr>
<td>Add Material Stored On-Site</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>Subtract Materials Installed On-Site</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>Subtotal</td>
<td>$ -</td>
<td>$ 84,739.10</td>
</tr>
<tr>
<td>Retainage (5%)</td>
<td>$ -</td>
<td>$0.00</td>
</tr>
<tr>
<td>Previous Payments</td>
<td colspan="2">$80,502.14</td>
</tr>
<tr>
<td>Amount Due</td>
<td>$ -</td>
<td>$ 4,236.96</td>
</tr>
</table>
Estimated % of Job Complete Based on Amount Earned/Contract Amount only 96%
This does not constitute work completed to date
Is Contractor's Construction Progress on Schedule? YES NO N/A ✗
I hereby certify that I have carefully inspected the work and as a result of my inspection and to the best of my knowledge and belief, the quantities shown in this estimate are correct and have not been shown in previous estimates and the work has been performed in accordance with the contract documents.
HART-FREDERICK CONSULTANTS P.C.
By:
Title: Project Engineer
Date: October 10, 2022
Approved by Owner's Representative:
By: ____________________________
Title: ____________________________
(Additional signatures – if required)
By: ____________________________
Title: ____________________________