DATE: October 10, 2022 Hart-Frederick Consultants P.C. 510 East State Street P.O. Box 560 Tiffin, Iowa 52340-0560 Trail Phase 6 Project City of Tiffin HFC#16218.200 PAY ESTIMATE PROCEDURES 1. Sign All Copies as Indicated 2. Send One Copy With Payment of $ 4,236.96 to CONTRACTOR Vieth Construction Corp. 6419 Nordic Dr. Cedar Falls Ia 50613 3. Return TWO Copies to Hart-Frederick Consultants (address above) 4. Retain One Copy for Your Records Please call (319) 545-7215 with any questions. Thank-you.