 Add fluoride room freeze stat -– instrument, (1) PLC I/O + programming to 10-SCC-1 Removals:  Removed HWA manhole float switch  Removed (1) spare backup PLC and (1) spare backup HMI, fully programmed (not sure if this was included)  Removed ERMS switch from 20-SCC-1 Attachments: (List attached documents that support description.) Refer to general construction contract documents and procurement documents. REQUESTED BY: MSA Professional Services, Inc. Name G:\13\13603\13603021\Documents\CONSTRUCTION BULLETINS\CB # - SYSTEM INTEGRATION ITEMS\13603021 TIFFIN WTP CB# Proposal Request 2025-04-22.docx