contract agreement · K-7
Consideration of Pay Applications #4 and #5 – GHS Development/Maxwell Construction, Tiffin Heights West Watermain Extension – Motion to Approve
Page 1 of 2
Text from the PDF text layer; check the PDF for anything that matters.To: GHS Development Customer #: SB24-051
Jason Dumont
[email protected] Date: 4/1/2025
P.O. Box 78 North Liberty, IA 52317
Work Completed Through: 3/31/2025
Project: Tiffin Heights West, Off-Site Public Improvements APPLICATION # 4 Project # 24-051
SANITARY SEWER ITEMS TOTALS THIS PERIOD COMPLETED TO DATE
Item # Description Quantity Unit Unit Price Total Quantity Cost Quantity Cost %
1 Sanitary Sewer, PVC Truss, 8-inch 265 LF $ 48.00 $ 12,720.00 8.00 $ 384.00 8.00 $ 384.00 3.02%
2 Sanitary Sewer, PVC Truss, 10-inch 2,751 LF $ 68.00 $ 187,068.00 1,351.00 $ 91,868.00 2,751.00 $ 187,068.00 100.00%
3 SW-301 Sanitary Sewer Manhole (9 Structures) 107.78 VF $ 420.00 $ 45,267.60 61.70 $ 25,914.00 107.78 $ 45,267.60 100.00%
4 Connect to Existing Sanitary Sewer Manhole 1 EA $ 1,500.00 $ 1,500.00 0.00 $ - 1.00 $ 1,500.00 100.00%
5 Gas Crossings 2 EA $ 2,200.00 $ 4,400.00 0.00 $ - 1.00 $ 2,200.00 50.00%
6 Sanitary Sewer Televising 3,016 LF $ 2.00 $ 6,032.00 0.00 $ - 0.00 $ - 0.00%
7 Sanitary Sewer Testing 1 LS $ 850.00 $ 850.00 0.40 $ 340.00 0.40 $ 340.00 40.00%
8 Driveway/Roadway Granular Surfacing 89 TON $ 30.00 $ 2,670.00 49.00 $ 1,470.00 89.00 $ 2,670.00 100.00%
9 Granular Trench Backfill 75 LF $ 205.00 $ 15,375.00 55.00 $ 11,275.00 75.00 $ 15,375.00 100.00%
10 Sanitary Compacted Trench Backfill 2,941 LF $ 12.00 $ 35,292.00 1,500.00 $ 18,000.00 2,900.00 $ 34,800.00 98.61%
SANITARY SEWER TOTAL $ 311,174.60 $ 118,506.00 $ 236,759.60
WATER ITEMS TOTALS THIS PERIOD COMPLETED TO DATE
Item # Description Quantity Unit Unit Price Total Quantity Cost Quantity Cost %
1 8" PVC Watermain 20 LF $ 33.00 $ 660.00 0.00 $ - 20.00 $ 660.00 100.00%
2 12" PVC Watermain 2,418 LF $ 63.00 $ 152,334.00 0.00 $ - 2,418.00 $ 152,334.00 100.00%
3 12" PVC Restrained Joint Watermain 590 LF $ 80.00 $ 47,200.00 0.00 $ - 590.00 $ 47,200.00 100.00%
4 Directional Drill 12" Watermain 113 LF $ 135.00 $ 15,255.00 0.00 $ - 113.00 $ 15,255.00 100.00%
5 Bore & Jack 12" Watermain w/22" Casing 105 LF $ 770.00 $ 80,850.00 0.00 $ - 105.00 $ 80,850.00 100.00%
6 8" Gate Valve 1 EA $ 2,500.00 $ 2,500.00 0.00 $ - 1.00 $ 2,500.00 100.00%
7 12" Gate Valve 14 EA $ 4,350.00 $ 60,900.00 0.00 $ - 14.00 $ 60,900.00 100.00%
8 Fire Hydrant Assembly 8 EA $ 7,800.00 $ 62,400.00 0.00 $ - 8.00 $ 62,400.00 100.00%
9 Connection to the Existing Watermain 2 EA $ 350.00 $ 700.00 0.00 $ - 2.00 $ 700.00 100.00%
10 Miscellaneous Water Fittings 1 LS $ 33,600.00 $ 33,600.00 0.00 $ - 1.00 $ 33,600.00 100.00%
11 Water Testing 1 LS $ 900.00 $ 900.00 0.00 $ - 1.00 $ 900.00 100.00%
12 Watermain Compacted Trench Backfill 3,028 LF $ 8.00 $ 24,224.00 0.00 $ - 3,028.00 $ 24,224.00 100.00%
WATER TOTAL $ 481,523.00 $ - $ 481,523.00
MISCELLANEOUS ITEMS TOTALS THIS PERIOD COMPLETED TO DATE
Item # Description Quantity Unit Unit Price Total Quantity Cost Quantity Cost %
1 Traffic Control 1 LS $ 12,000.00 $ 12,000.00 0.50 $ 6,000.00 1.00 $ 12,000.00 100.00%
2 Rock Check Dam 24 EA $ 750.00 $ 18,000.00 6.00 $ 4,500.00 12.00 $ 9,000.00 50.00%
3 Class D Rip Rap 52 TON $ 60.00 $ 3,120.00 0.00 $ - 0.00 $ - 0.00%
4 Silt fence 1,475 LF $ 2.00 $ 2,950.00 0.00 $ - 1,127.00 $ 2,254.00 76.41%
5 Filter Sock Inlet Protection 7 EA $ 75.00 $ 525.00 0.00 $ - 4.00 $ 300.00 57.14%
6 Seeding Work 4.8 ACRE $ 4,700.00 $ 22,560.00 0.00 $ - 0.83 $ 3,901.00 17.29%
7 Finish Grading 1 LS $ 16,000.00 $ 16,000.00 0.25 $ 4,000.00 0.75 $ 12,000.00 75.00%
8 SWPPP Maintenance 1 LS $ 2,800.00 $ 2,800.00 0.35 $ 980.00 0.70 $ 1,960.00 70.00%
MISCELLANEOUS TOTAL $ 77,955.00 $ 15,480.00 $ 41,415.00
EXTRA WORK ORDERS TOTALS THIS PERIOD COMPLETED TO DATE
Item # Description Quantity Unit Unit Price Total Quantity Cost Quantity Cost %
1 Pipe Upsize: 8" Truss to 10" Truss Per City 1 LS $ 10,215.20 $ 10,215.20 1.00 $ 10,215.20 1.00 $ 10,215.20 100.00%
2 Trench Stabilization 33.33 TON $ 38.00 1,266.54 0.00 $ - 33.33 $ 1,266.54 100.00%
3 2" x 4" Oversized Material 56.08 TON $ 42.00 2,355.36 0.00 $ - 56.08 $ 2,355.36 100.00%
EXTRA WORK ORDER COST $ 13,837.10 $ 10,215.20 $ 13,837.10
Summary of Request
Total Contract $ 870,652.60 $ 133,986.00 $ 759,697.60
Extra Work Orders $ 13,837.10 $ 10,215.20 $ 13,837.10
Total Contract w/ EWOs $ 884,489.70 $ 144,201.20 $ 773,534.70 % Complete:
87.46%
Less Retainage of Completed Work (0%) $ -
Total Retainage / Dues $ -
Total Earned Less Retainage $ 773,534.70 To finish (w/ret.):
Less Previously Approved Pay Requests $ - $110,955.00
Previously Approved Pay Requests: PAID? DATE
Pay App #1 $ 500,923.00
Pay App #2 $ 70,952.10
Pay App #3 $ 57,458.40
Total Previously Approved Pay Requests $ 629,333.50 Balance Due This Month $ 144,201.20
Balance Overdue $ -
Total Balance Due $ 144,201.20
Thank you!
1 1/2% (18% per annum) per month late payment charge will be added to accounts 30 days past due.
67.5% PER DEVELOPER'S AGREEMENT = $97,335.81
Page 1 of 1
Sources
- revize: Attachment (RvOI4UG7yRiDeK7YoTpTpvMgBdA9KT.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-7 - Pay Application 4 and 5 - GHS-Maxwell - Tiffin Heights West.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-7 Consideration of Pay Applications #4 and #5 – GHS Development/Maxwell Construction,...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.