contract agreement · K-4
Consideration of Change Order #1 – Tricon Construction Group, Water Treatment Plant Upgrade – Motion to Approve
Page 3 of 7
Text from the PDF text layer; check the PDF for anything that matters. CONSTRUCTION BULLETIN No.1
REQUEST FOR PROPOSAL
CONTRACTOR: PROPOSAL REQUEST NO.: 1
Tricon General
Construction, Inc. DATE OF ISSUANCE: 04-23-2025
746 58th Ave Ct., SW
Cedar Rapids, IA 52404 CONTRACT FOR:
OWNER:
City of Tiffin CONTRACT DATED:
300 Railroad St
Tiffin, IA 52340 ENGINEER'S PROJECT NO: R013603021
PROJECT: ENGINEER: MSA Professional Services, Inc.
City of Tiffin (Name and Address) 400 Ice Harbor Dr, Ste 110
Water Treatment Plant Dubuque, IA 52001
Upgrade
Please submit an itemized proposal for changes in the Contract Sum and Contract Time for proposed modifications to the Contract
Documents described herein. Submit proposal within 10 business days or notify the Engineer in writing of the date on which you
anticipate submitting your proposal.
THIS IS NOT A CHANGE ORDER, A CONSTRUCTION CHANGE DIRECTIVE OR A DIRECTION TO PROCEED WITH THE WORK DESCRIBED
IN THE PROPOSED MODIFICATIONS.
Description:
Changes to the System Integrator Procurement Contract Documents. Please provide proposal to provide the following
changes to the System Integrator contract, installation and labor is not anticipated to impact on the general
construction contract. Because these items are included in the general construction contract:
Additions:
20-LP-1A lighting panel modifications (breakers, increase main breaker size)
20-LP-1B lighting panel modifications (breakers)
30-LP-1 lighting panel modifications (breakers)
Add aerator pit heater – breaker bucket with contactor in 20-MCC-1A (could use spare breaker without
contactor)
Moved PLC input from well 4 level transducer from 10-SCC-1 to 20-SCC-1 as a new input (it was determined
this was not already installed by owner)
Add Pre-Chlorine chemical flow meters - (2) PLC I/O + programming to 10-SCC-1
Add fluoride chemical scale - (1) PLC I/O + programming to 10-SCC-1
Add (2) fluoride chemical pumps - (8) PLC I/O + programming to 10-SCC-1
Add fluoride chemical flow meters - (2) PLC I/O + programming to 10-SCC-1
Add post chlorine and caustic chemical flow meters - (4) PLC I/O + programming to 20-SCC-1
Add fluoride temperature probe - instrument, (1) PLC I/O + programming to 10-SCC-1
Add Storage room occupancy sensor – instrument, (1) PLC I/O + programming to 10-SCC-1
Add fluoride room door switch – instrument, (1) PLC I/O + programming to 10-SCC-1
Add fluoride room fan/light control station – instrument, (2) PLC I/O + programming to 10-SCC-1
Add fluoride room fan/damper control – power relays, (2) PLC I/O + programming to 10-SCC-1
Add fluoride room light control – power relay + programming to 10-SCC-1
G:\13\13603\13603021\Documents\CONSTRUCTION BULLETINS\CB # - SYSTEM INTEGRATION ITEMS\13603021 TIFFIN WTP CB# Proposal Request 2025-04-22.docx
Sources
- revize: Attachment (3R1W5VEOEnpDNmpsjgVCBtNRV1vLLn.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-4 - Change Order 1 - Tricon - Water Treatment Plant.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Consideration of Change Order #1 – Tricon Construction Group, Water Treatment Plant...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.