CHANGE ORDER DATE: 16 June, 2025 Change Order No: 5 (FIVE) Agreement Date: 12/14/2023 PROJECT: Original Town Urbanization – Phase 3 HFC #18218.131 OWNER: Tiffin, IA CONTRACTOR: Rathje Construction Co. DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS: New water service and storm sewer for new development on former Slim’s site, See attachment for details. CONTRACT PRICE CHANGES: Original CONTRACT PRICE: $ 2,134,856.90 CONTRACT with LAST CHANGE ORDER: $ 2,216,900.51 THIS CHANGE ORDER AMOUNT: $ 12,907.49 NEW CONTRACT PRICE: $ 2,229,808.00 CONTRACT TIME CHANGES CONTRACT TIME (increased)(decreased): 2 Days NEW Completion Date: September 24, 2025 APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER. OWNER: CONTRACTOR: See Attached ENGINEER:

Sources

  • revize: Attachment (NGPHWRQLYdTm5hsUWZcoSU1sPfXNpz.pdf) — where it was found ↗ first seen Oct 12, 2026
  • sharepoint (K-2 - Change Order 5 - Rathje Construction - Original Town Phase 3.pdf) — where it was found ↗ first seen Oct 12, 2026

Attached to agenda item: K-2 Consideration of Change Order #5 – Rathje Construction, Original Town Urbanization...

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.