Consideration of Change Order #7 - Rathje Construction, Original Town Urbanization Project - Motion to Approve — Item Packet
Page 2 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 1 July, 2025
Change Order No: 7 (SEVEN)
Agreement Date: 12/14/2023
PROJECT: Original Town Urbanization – Phase 3 HFC #18218.131
OWNER: Tiffin, IA
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Unstable subgrade materials have been encountered on the project. The areas are identified as: Third Street Sta. 4+00 - 4+75, Main Street Sta 8+83 - 9+25, Sta. 10+10 - 10+25. An additional 6-inches of subbase material with geogrid is recommended. A total area of approximately 513.33 SY requires Subgrade Stabilization. Prices for this type of work were established in CO#1.
Polymer Grid Subgrade Stabilization 513.33SY @ $3.50 = $1,796.66
6-Inch Subgrade Stabilization 513.33SY @ $75.00 = $38,499.75
Additional Excavation Class 10 Waste 85.56CY @ $12.50 = $1,069.50
Estimated Total = $41,365.91
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $ 2,134,856.90
CONTRACT with LAST CHANGE ORDER: $ 2,253,983.00
THIS CHANGE ORDER AMOUNT: $ 41,365.91
NEW CONTRACT PRICE: $ 2,295,348.91
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 2 Days
NEW Completion Date: September 30, 2025
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: Verbally Verified and Approved by Dan Scofield 1 July, 2025
ENGINEER:
Sources
- revize: Item Packet (IdZm81oNs2V2altUUJR9tKSOWAmtCI.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-2 - Staff Report - Change Order 7 Rathje.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Consideration of Change Order #7 - Rathje Construction, Original Town Urbanization...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.