Discussion and Consideration of Pay Application #2 – Tricon Construction Group, Water Treatment Plant Upgrades – Motion to Approve
Page 12 of 12
Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades- City of Tiffin
Contract:
Application No.: 2 Application Period: From 08/01/25 to 09/30/25 Application Date: 09/26/25
Change Orders
Change Order #1 3 2
Electrical Controls Changes $12,420.34 - 12,420.34
Change Order Totals| $ 12,420.34 | $ - $ - S - $ - 0%| $ 12,420.34
Original Contract and Change Orders
Project Totals| $__ 12,194,973.34
| $ 482,234.02
| $ 319,449.82
|$ - |$ 801,683.84 7%|$ 11,393,289.50
EJCDC” C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved. 00 62 76 - 10 of 10 \FILESERVER|Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\Pay is\Pay
Sources
- revize: Attachment (sJkAosKmF3YbZCU8nafSLzkrjB6ds2.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-3 - Staff Report - Pay App #2 - Tricon Construction Group - Water Treatment Plant Upgrades.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #2 – Tricon Construction Group, Water...