contract agreement · K-3
Discussion and Consideration of Pay Application #2 – Tricon Construction Group, Water Treatment Plant Upgrades – Motion to Approve
Page 11 of 12
Text read by the vision model; check the PDF for anything that matters.Progress Estimate - Lump Sum Work
<table>
<tr>
<th>Owner:</th>
<td>City of Tiffin</td>
<th>Owner's Project No.:</th>
<td></td>
</tr>
<tr>
<th>Engineer:</th>
<td>MSA Professional Services</td>
<th>Engineer's Project No.:</th>
<td>13603016</td>
</tr>
<tr>
<th>Contractor:</th>
<td>Tricon Construction Group</td>
<th>Contractor's Project No.:</th>
<td></td>
</tr>
<tr>
<th>Project:</th>
<td>Water Treatment Plant Upgrades - City of Tiffin</td>
<th colspan="2"></th>
</tr>
<tr>
<th>Contract:</th>
<td></td>
<th colspan="2"></th>
</tr>
</table>
<table>
<tr>
<th>Application No.: 2</th>
<th>Application Period:</th>
<th>From</th>
<th>08/01/25</th>
<th>to</th>
<th>09/30/25</th>
<th>Application Date:</th>
<th>09/26/25</th>
</tr>
<tr>
<th colspan="2">Original Contract Totals</th>
<th>$ 12,182,553.00</th>
<th>$ 482,234.02</th>
<th>$ 319,449.82</th>
<th>$ -</th>
<th>$ 801,683.84</th>
<th>7% $ 11,380,869.16</th>
</tr>
</table>
Sources
- revize: Attachment (sJkAosKmF3YbZCU8nafSLzkrjB6ds2.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-3 - Staff Report - Pay App #2 - Tricon Construction Group - Water Treatment Plant Upgrades.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #2 – Tricon Construction Group, Water...