staff report memo · L-3
Tiffin Recreation Center Monthly Report
Page 8 of 19
Text from the PDF text layer; check the PDF for anything that matters.Construction Summary
Schedule Update
Scheduled October Activities: Scheduled November Activities:
• Footings (100%) • Erection of pre-engineered metal building
• Foundation walls (95%) • Underground electrical
• Foundation backfill (80%) • Underground plumbing
• Exterior storm piping (75%) • Stoop walls and topping slabs
• Elevator shaft (100% complete as of 11/5) • Additional water main work (ASI-04)
Manpower Report
List of major subcontractors & number of employees onsite:
Total number of employees: 25
• Cedar Valley Steel - 2
• Freeman Construction - 2
• Miron Concrete - 8
• Miron Construction Manager - 2
• Seehase Masonry - 7
• SG Construction – 2
• Schrader Excavating & Grading Co – 2
Delays
• Weather – See Daily Log Weather Report
‒ 1 rain day in October
Weather Delays (Construction)
Scheduled Occurred Left
12 1 11
• Materials & Labor
‒ None at this time
Key Issues / Concerns & Recommended Action Steps
• Inspections for rebar and concrete during foundation work
• Coordination of openings in CMU Deliver unmatched quality,
create meaningful
connections, and craft
unforgettable experiences in
everything we do. Capture
what truly matters and find
ways to inspire.
Owner Progress Report | 250120 October 2025 Miron Construction Co., Inc.
|8
Sources
- revize: Attachment (GUStiweSiMHBuDC7PDhsDsVSgrKkbF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-3 - Tiffin Recreation Center Monthly Report - October 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report