packet
Packet: Tiffin Regular City Council Meeting (12/02/2025)
Dated December 2, 2025City Council — regular meeting, December 2, 2025 160 pages
Ord. 2025-522, Ord. 2025-523, Res. 2025-089, Res. 2025-090, Res. 2025-091
Page 144 of 160
Text read by the vision model; check the PDF for anything that matters.APPLICATION AND CERTIFICATE FOR PAYMENT
CONTRACTOR: Cornerstone Excavating, Inc.
PO Box 928
Washington, IA 52353
SUBCONTRACTOR:
CONTRACT FOR: City of Tiffin
PROJECT: EARTH STOCKPILE SPREAD
JOH067
TIFFIN, IA
APPLICATION NUMBER: 2
APPLICATION DATE: 11/12/25
PERIOD TO: 11/12/25
PROJECT NOS.:
CONTRACT DATE:
VIA CONSTRUCTION MANAGER: BJ Miller
VIA ARCHITECT:
Distribution to:
OWNER
CONSTRUCTION MANAGER
ARCHITECT
CONTRACTOR
CONTRACTOR'S APPLICATION FOR PAYMENT
Application is made for payment, as shown below, in accordance with the Contract. Continuation Sheet, AIA Document G703, is attached.
1. ORIGINAL CONTRACT SUM $138,050.00
2. Net Change By Change Orders $14,825.25
3. CONTRACT SUM TO DATE (Line 1 + 2) $152,875.25
4. TOTAL COMPLETED & STORED TO DATE (Column G on G703) $151,652.75
5. RETAINAGE:
a. 3% % of Completed Work (Columns 'D & E on G703) $4,549.58
b. 3% % of Stored Material (Column F on G703) $0.00
Total Retainage (Line 5a + 5b or Total in Column 1 of G703) $4,549.58
6. TOTAL EARNED LESS RETAINAGE (Line 4 less Line 5 Total) $147,103.17
7. LESS PREVIOUS CERTIFICATES FOR PAYMENT (Line 6 from prior Certificate) $141,283.17
8. CURRENT PAYMENT DUE $5,820.00
9. BALANCE TO FINISH, INCLUDING RETAINAGE (Line 3 less Line 6) $5,772.08
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief, the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
CONTRACTOR:
BY: [signature] BJ Miller
DATE: 11/12/25
State of: ___________________________ County of: ___________________________
Subscribed and sworn before me this day of ________________, 2016
Notary Public:
My Commission Expires: ___________________________
CERTIFICATE FOR PAYMENT
In accordance with the Contract Documents, based on on-site observations and the data comprising the above application, the Construction Manager certifies that to the best of his knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the AMOUNT CERTIFIED.
AMOUNT CERTIFIED............................. $ 5,820.00
(Attach explanation if amount certified differs from the amount applied for. Initial all figures on this Application and on the Continuation Sheet that changed to conform to the amount certified.)
CONSTRUCTION MGR:
By: ____________________________ Date: ________________
ARCHITECT:
By: ____________________________ Date: 11/14/2025
This certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the Contractor named herein. Issuance, payment and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.
Sheets in this document
- p. 22 Concept Design · Streamline Architects · Tiffin Events Center
- p. 23 Concept Design · Streamline Architects · Tiffin Events Center
- p. 24 Concept Design · Streamline Architects · Tiffin Events Center
- p. 25 Concept Design · Streamline Architects · Tiffin Events Center
- p. 26 Concept Design · Streamline Architects · Tiffin Events Center
- p. 27 Concept Design · Streamline Architects · Tiffin Events Center
- p. 28 Concept Design · Streamline Architects · Tiffin Events Center
- p. 29 Concept Design · Gallant Design
- p. 30 Concept Design | Tiffin Events Center · Streamline Architects
- p. 31 Concept Design · Streamline Architects · Tiffin Events Center
- p. 32 Concept Design · Streamline Architects · Tiffin Events Center
- p. 33 Concept Design · Gallant Design
- p. 34 Concept Design · Streamline Architects · Tiffin Events Center
- p. 35 Floor Plan
- p. 36 C120 · General Notes and Details · MMS Consultants
- p. 45 A.200 · South Elevation
- p. 46 Floor Plan
- p. 47 Floor Plan · Basement
- p. 48 A.200 · South Elevation
- p. 49 A.201 · North Elevation
- p. 50 Floor Plan · Level 2
- p. 51 A.200 · Building Elevations
- p. 52 Floor Plans
- p. 53 C200 · Site Layout · Iowa DOT
- p. 54 C300 · Site Utilities Plan
- p. 55 C301 · Site Utilities Plan
- p. 56 Revised Site P
- p. 57 Preliminary Plat
- p. 58 2 · Road Typical Section
- p. 59 3 · Revised Phasing & Utility Layout
- p. 71 Concept Design · Streamline Architects · Tiffin Events Center
- p. 72 Concept Design · Streamline Architects · Tiffin Events Center
- p. 73 Concept Design · Streamline Architects · Tiffin Events Center
- p. 74 Concept Design · Streamline Architects · Tiffin Events Center
- p. 75 Concept Design · Streamline Architects · Tiffin Events Center
- p. 76 Concept Design · Streamline Architects · Tiffin Events Center
- p. 77 Concept Design · Streamline Architects · Tiffin Events Center
- p. 78 Concept Design · Gallant Design
- p. 79 Concept Design | Tiffin Events Center · Streamline Architects
- p. 80 Concept Design · Streamline Architects · Tiffin Events Center
- p. 81 Concept Design · Streamline Architects · Tiffin Events Center
- p. 82 Concept Design · Gallant Design
- p. 83 Concept Design · Streamline Architects · Tiffin Events Center
- p. 84 Floor Plan
- p. 85 C120 · General Notes and Details · MMS Consultants
- p. 94 A.200 · South Elevation
- p. 95 Floor Plan
- p. 96 Floor Plan · Basement
- p. 97 A.200 · South Elevation
- p. 98 A.201 · North Elevation
- p. 99 Floor Plans
- p. 100 A.200 · Building Elevations
- p. 101 Floor Plans
- p. 102 C200 · Site Layout · Iowa DOT
- p. 103 C300 · Site Utilities Plan
- p. 104 C301 · Site Utilities South
- p. 105 Revised Site Plan
- p. 106 Preliminary Plat
- p. 107 2 · Road Typical Section
- p. 108 3 · Address City Comments Revised Phasing & Utility Layout
Sources
- revize: Agenda packet (packet_2025-12-02_4b734c31-25e7-4dd6-9fb9-361df96c5fac.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 20, 2026. Built from the archive's documents; see how the data is built.