Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 11/28/2025
Miron Construction Co., Inc. Data Date: 28-Nov-25
Page 3 of 4
250120-26PM 20251128
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
1560 AAAMECH 1570, 1660 2nd Floor In Wal Rough In - MEP 5 5 11-Mar-26 17-Mar-26
1550
1580 AAAMECH 1390, 1680 Gym Area Overhead Rough In - MEP 15 15 11-Mar-26 31-Mar-26
1570
2840 MIRON CONC 1360 2940, Prep/Pour/Strip Slab on Grade - Green 3 3 11-Mar-26 13-Mar-26
2830
2430 TSF 2350, 1960 Steel - Sequence 9 Mechanical Screens Instal 15 15 13-Mar-26 02-Apr-26
2850
2830 MIRON CONC 2840 2410, Prep/Pour/Strip Slab on Grade - Brown 3 3 16-Mar-26 18-Mar-26
1990
1520 PEARSON 2980, 1530, 1st Floor Interior Steel Stud Framing 10 10 18-Mar-26 31-Mar-26
1360, 2340
1540 ILTENS 1430
1360, 1530, 1st Floor Overhead Rough In - Mechanical 15 15 18-Mar-26 07-Apr-26
1300 2010
2340 GENTRADES 1520, 1660, Hol ow Metal Frame Instal ation 3 3 18-Mar-26 20-Mar-26
1550, 1600
1990 MERIT 2980
2110, 2890 PEMB - Interior Liner Panels 15 15 19-Mar-26 08-Apr-26
2830
2410 TSF 2830, 2420 Steel - Sequence 7 Running Track Stair Intal /Detail 5 5 19-Mar-26 25-Mar-26
2400,
2940 TRI CITY FP 2330
2840 1630 1st Floor Fire Protection 15 15 19-Mar-26 08-Apr-26
1530 AAAMECH 1540, 1600 1st Floor In Wal Rough In - MEP 15 15 23-Mar-26 10-Apr-26
1520
1660 PEARSON 1560, 1670 2nd Floor Drywal - Hang 3 3 23-Mar-26 25-Mar-26
2340
1670 PEARSON 1660 1680 2nd Floor Drywal - Tape and Sand 5 5 26-Mar-26 01-Apr-26
1680 YOUNGS 2930, 3010, 2nd Floor Paint 8 8 02-Apr-26 13-Apr-26
2420, 2910,
3010 APPLEBY 1670,
1680 2890,
1700 2nd Floor Wal Tile 8 8 06-Apr-26 15-Apr-26
2010 PRICEELEC 1650, 1830 Permenant Power 1 1 08-Apr-26 08-Apr-26
1540
1830 OTIS 2010, 2120, Elevator Instal ation 15 15 09-Apr-26 29-Apr-26
1270 1740
1600 PEARSON 1840, 1610 1st Floor Drywal - Hang 10 10 13-Apr-26 24-Apr-26
1530,
2890 PRICEELEC 2340
1990, 1760 2nd Floor - Electrical Trim and Lights 10 10 14-Apr-26 27-Apr-26
1680
2900 ILTENS 1680 1820 2nd Floor - Fabric Duct and Diffusers 8 8 14-Apr-26 23-Apr-26
2910 H2I 1680 1720 Gym Equipment - Instal ation 20 20 14-Apr-26 11-May-26
1700 AAAMECH 3010, 2090 2nd Floor Plumbing Fixtures 5 5 16-Apr-26 22-Apr-26
1680
1610 PEARSON 1600 1620 1st Floor Drywal - Tape and Sand 15 15 27-Apr-26 15-May-26
1620 YOUNGS 1470, 3020, 1st Floor Paint 8 8 18-May-26 28-May-26
1610 2870,
3020 APPLEBY 1620 2080,
1640 1st Floor Wal Tile 15 15 21-May-26 11-Jun-26
1630 HARGERS 2940, 2870, 1st Floor Ceiling Tile - Grid 15 15 29-May-26 18-Jun-26
1620 2880,
3080 MIRON DOOR 3000, 1740,
2090 Door and Hardware Instal ation 8 8 29-May-26 09-Jun-26
1620
2870 PRICEELEC 1630, 1760 1st Floor - Electrical Trim and Lig hts 10 10 05-Jun-26 18-Jun-26
1620
2880 ILTENS 1630 1820 1st Floor - Diffusers 10 10 05-Jun-26 18-Jun-26
1640 AAAMECH 3020, 2090, 1st Floor Plumbing Fixtures 5 5 19-Jun-26 25-Jun-26
1630 1650
1650 CEILING 1640 1820 1st Floor Ceiling Tile - Drop 2 2 26-Jun-26 29-Jun-26
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sheets in this document
- p. 17 Concept Design · Streamline Architects · Tiffin Events Center
- p. 18 Concept Design · Streamline Architects · Tiffin Events Center
- p. 19 Concept Design · Streamline Architects · Tiffin Events Center
- p. 20 Concept Design · Streamline Architects · Tiffin Events Center
- p. 21 Concept Design · Streamline Architects · Tiffin Events Center
- p. 22 Concept Design · Streamline Architects · Tiffin Events Center
- p. 23 Concept Design · Streamline Architects · Tiffin Events Center
- p. 24 Concept Design · Hume Architects · Tiffin Events Center
- p. 25 Concept Design · Streamline Architects · Tiffin Events Center
- p. 26 Concept Design · Streamline Architects · Tiffin Events Center
- p. 27 Concept Design · Streamline Architects · Tiffin Events Center
- p. 28 Concept Design · Hume Architects · Tiffin Events Center
- p. 30 Floor Plan
- p. 31 C120 · Final OPD Site Plan · MMS Consultants · Park Place City Center - Part One, Phase Four
- p. 38 A.200 · West Elevation
- p. 39 A.100 · Floor Plan · Level 2
- p. 40 Floor Plan · Basement
- p. 41 A.200 · Building Elevations
- p. 42 A.201 · East Elevation
- p. 43 Floor Plan · Level 2
- p. 44 A.200 · Building Elevations
- p. 45 Floor Plan · Level 2
- p. 46 C200 · Site Layout Plan · Iowa DOT · Constructed as Part of Phase I Improvements
- p. 47 C300 · Site Utilities Plan North · Grove Park Rowhomes
- p. 48 C301 · Site Utilities Plan South · Grove Park Rowhomes
- p. 49 Landscape Plan
- p. 50 Preliminary Plat · Project Total
- p. 51 2 · Preliminary Plat · Grove Park Rowhomes
- p. 52 3 · Preliminary Plat
- p. 91 map
- p. 98 City of Tiffin FY 25-26 Town Hours by Month (chart; data on p. 97)
- p. 134 Site Concrete
- p. 135 Gym Floor and Slab on Grade · MEP