Text from the PDF text layer; check the PDF for anything that matters.Executive Summary
Overview
The building is taking shape! The Pre-Engineered Metal Building (PEMB) erection began mid-November. The large
columns and beams are defining the shape of the building. All foundation work has been completed including
mechanical pad and stoop walls. Progress is being made on the topping slabs for the mechanical pads and stoops.
Our site utility contractor wrapped up their contract work with the additional fire hydrants and storm outflow on the
Southeast side.
Major Milestones / Accomplishments
• Site Utility contractor is complete with all contract work
• The start of the Pre-Engineered Metal Building (PEMB)
• Underground plumbing is complete
• Foundations are complete
Upcoming Milestones
• Interior steel delivery and erection
• Building enclosure – End of January 2026
Key Issues and Concerns
• Applying for utility applications to begin coordinating with utility companies
‒ Gas (MidAmercian Energy), design is complete, and payment was sent out
• Weather and building enclosure to pour slabs on grades
Be authentic, lead with
humility, and recognize the
needs of others. Care for one
another and extend a helping
hand wherever it’s needed.
Honor our history.
Owner Progress Report | 250120 November 2025 Miron Construction Co., Inc. | 5
Sheets in this document
- p. 17 Concept Design · Streamline Architects · Tiffin Events Center
- p. 18 Concept Design · Streamline Architects · Tiffin Events Center
- p. 19 Concept Design · Streamline Architects · Tiffin Events Center
- p. 20 Concept Design · Streamline Architects · Tiffin Events Center
- p. 21 Concept Design · Streamline Architects · Tiffin Events Center
- p. 22 Concept Design · Streamline Architects · Tiffin Events Center
- p. 23 Concept Design · Streamline Architects · Tiffin Events Center
- p. 24 Concept Design · Hume Architects · Tiffin Events Center
- p. 25 Concept Design · Streamline Architects · Tiffin Events Center
- p. 26 Concept Design · Streamline Architects · Tiffin Events Center
- p. 27 Concept Design · Streamline Architects · Tiffin Events Center
- p. 28 Concept Design · Hume Architects · Tiffin Events Center
- p. 30 Floor Plan
- p. 31 C120 · Final OPD Site Plan · MMS Consultants · Park Place City Center - Part One, Phase Four
- p. 38 A.200 · West Elevation
- p. 39 A.100 · Floor Plan · Level 2
- p. 40 Floor Plan · Basement
- p. 41 A.200 · Building Elevations
- p. 42 A.201 · East Elevation
- p. 43 Floor Plan · Level 2
- p. 44 A.200 · Building Elevations
- p. 45 Floor Plan · Level 2
- p. 46 C200 · Site Layout Plan · Iowa DOT · Constructed as Part of Phase I Improvements
- p. 47 C300 · Site Utilities Plan North · Grove Park Rowhomes
- p. 48 C301 · Site Utilities Plan South · Grove Park Rowhomes
- p. 49 Landscape Plan
- p. 50 Preliminary Plat · Project Total
- p. 51 2 · Preliminary Plat · Grove Park Rowhomes
- p. 52 3 · Preliminary Plat
- p. 91 map
- p. 98 City of Tiffin FY 25-26 Town Hours by Month (chart; data on p. 97)
- p. 134 Site Concrete
- p. 135 Gym Floor and Slab on Grade · MEP
Sources
- revize: Agenda packet (packet_2025-12-16_68f8c41f-ab61-420c-9e5a-6c45e968ae57.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 21, 2026. Built from the archive's documents; see how the data is built.