ON-GOING PROJECTS
REVERSE OSMOSIS WATER TREATMENT PLANT DESIGN – CLINT WIENEN
The concrete electrical pads have been completed, and the new generator has been delivered and placed.
The footing for the new RO building has been poured and is in the curing process. Next on the schedule is
to install the electrical manholes and complete work in the existing building. Regular construction meetings
have been scheduled to ensure project progress.
A Water Treatment Financial Assistance Program (WTFAP) grant application in the amount of $500,000 was
submitted to Iowa Finance Authority on October 21st. Anticipated award announcements is in
December/January.
HIGHWAY 6 CONCEPT AND COST ESTIMATE – JAMES WATTERS
MSA presented costs to Council at November 18th meeting for the following items:
1. Fully Signalized Intersection - $400-$435k per intersection
2. Installation of underground equipment for future signalized intersection at Croell Ave = $80-$100k
Council was split as to whether to fully signalize Croell Ave now or wait until future traffic growth warrants
signalization. It was brought up that the left turn movement onto EB US 6 would still be present with a non-signalized
option at Croell Ave and US 6 and whether public feedback would continue to be received on the safety of this
intersection without signalization.
There was also discussion from council as to whether an enhanced pedestrian crossing should be implemented at
Stephens St in the form of a High-Intensity Activated Crosswalk system (HAWK Signal). See below image.
PROJECT UPDATE
Page 1 of 5
Sources
- revize: Attachment (8JG7WgsUxgnGIOvVPoAp6Nu5sH3fWw.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-1 - City Engineer Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 City Engineer’s Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.