Resolution 2026-002 – A Resolution Approving the Developer’s Agreement with Grove Park Row Homes, LLC, for the Grove Park Planned Development Overlay Site District
Dated January 6, 2026City Council — regular meeting, January 6, 2026 11 pages
Ord. 2025-523, Res. 2026-002, Res. 2026-001
Page 4 of 11
Text from the PDF text layer; check the PDF for anything that matters.become a lien on all individual properties located within the planned development in favor of the
City.
G. Phasing. The project shall be constructed pursuant to the phasing plan
shown on Exhibit A. Construction of Phase 2 shall not begin until Phase 1 is complete.
Construction on Phase 3 shall not begin until Phases 1 and 2 are complete. If Owner wishes to
begin construction on the building shown in Phase 2 prior to Phase 1 being completed, Owner
may make this request to the Building Official and City Administrator. The Building Official and
City Administrator may allow such construction to begin at their sole discretion. Owner shall
furnish any information and documents requested by Building Official and City Administrator
regarding Owner’s request.
H. Parking. Owner may construct additional parking spaces on the Site, as
depicted on page 1 of Exhibit A by the light grey spaces in the northwest corner of the site and
south and north of the storm water detention facility. Owner may construct said parking spaces
without further approval from the City.
I. Building Permits. A Building permit may be applied for and may be issued
after this agreement is executed by all parties. However, only non-combustible material, as defined
by the Building Official, may be used in construction. Upon the following conditions being met,
construction pursuant to the building permit, including combustible material, may continue: (i)
Construction of the improvements in Paragraph E above in accordance with applicable standards,
(ii) formal acceptance by the City of the improvements in Paragraph E above; and (iii)
establishment of a temporary access to the Site for the fire department that serves Tiffin, as
approved by the City and the Tiffin Fire Association Chief.
J. Storm Water Management. Owner shall submit to the City, for approval
by the City Engineer, a storm water management plan which will identify the drainage of this
development and specify the manner in which storm water, drainage and runoff will be
accommodated. The storm water management plan must be submitted and approved by the City
Engineer prior to the issuance of a building permit for the site. Owner agrees to dispose of all
storm water through the approved storm water and drainageway system as set forth in the storm
water management plan. The design and construction of the storm water sewer system and storm
water detention basin, if required by the City for this development, shall be in compliance with
the City’s current storm water management ordinances and policies. The storm water sewer
system will be installed according to the Design Standards adopted by the City. Owner shall
provide for the installation of any storm water detention facility. All storm water sewer
improvements within the OPD shall be installed and maintained by Owner or its successors and
assigns. If Owner or its successors and assigns fails to maintain the storm water sewer
improvements, the City may assess each unit or lot in the OPD equally for any maintenance costs
in the same manner as property taxes and without further notice.
3
Sources
- revize: Attachment (ctttJ2FTzyYv8IcP0uFjHP1SjMvqsQ.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (I-2 - Resolution 2026-002 - Approving Developer's Agreement for Grove Park Row Homes.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: I-2 Resolution 2026-002 – A Resolution Approving the Developer’s Agreement with Grove Park...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.