staff report memo · L-4
Tiffin Recreation Center - Project Update
Page 8 of 19
Text from the PDF text layer; check the PDF for anything that matters.Construction Summary
Schedule Update
Scheduled December Activities: Scheduled January Activities:
• Foundation backfill (95%) • 2nd floor interior steel
• Erection of pre-engineered metal building (25%) • Locker Room CMU
• PEMB Roofing (0%) • PEMB roofing
• PEMB exterior metal panels (10%) • PEMB exterior metal panels
• Stoop topping slabs (100%)
• Locker Room CMU (85%)
Manpower Report
List of major subcontractors & number of employees onsite:
Total number of employees: 32
• AAA Mechanical – 1 • Price Electric – 2
• Cedar Valley Steel – 4 • Seehase Masonry - 7
• Merit Construction – 1 • SG Construction – 8
• Miron Concrete - 6 • Schrader Excavating & Grading Co – 1
• Miron Construction Manager - 2
Delays
• Weather – See Daily Log Weather Report
‒ 3 days in December
• 12/04/25 – Dangerous cold temperatures
• 12/18/25 – Rain in morning and high winds in afternoon (25-30mph sustained, gust up to 45mph)
• 12/29/25 – High winds (25mph sustained, gust 40+mph
Weather Delays (Construction)
Scheduled Occurred Left
12 5 7
• Materials & Labor
‒ Type C metal panel – delivery on 1/20/26
Deliver unmatched quality,
Key Issues / Concerns & Recommended Action Steps
create meaningful
• Coordination of openings in CMU
connections, and craft
• Installation progress of exterior metal panels and roof
unforgettable experiences in
everything we do. Capture
what truly matters and find
ways to inspire.
Owner Progress Report | 250120 December 2025 Miron Construction Co., Inc. | 8
Sources
- revize: Report (3hLTHJ2MqwS4Ba7UZK4nO46c2ZypMU.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - 250120 Tiffin Recreation Center Monthly Report - December 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-4 Tiffin Recreation Center - Project Update
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.