staff report memo · L-4
Tiffin Recreation Center - Project Update
Page 5 of 19
Text from the PDF text layer; check the PDF for anything that matters.Executive Summary
Overview
Happy New Year and welcome to the project completion year! The pre-engineered building installers have been busy!
The skeleton of the building is completed. They are getting the building ready for siding by installing jambs were the
horizontal siding will go and installing strapping on the underside of the roof. Metal panels on the North have started
and will continue wrapping around the building. The masons are wrapping up the locker rooms and working well with
the plumber and electrician to make sure in wall rough-in’s are completed. The steel beams, that the track hangs from
are installed as well. Looking ahead in January, the roof and siding will continue. We will also start steel erection for
the 2nd floor.
Major Milestones / Accomplishments
• Pre-engineered building erected
• Exterior metal siding has started
Upcoming Milestones
• Building enclosure
Key Issues and Concerns
• Color selection of AF-2
• Electrical and Gas service to building
• Weather and building enclosure to pour slabs on grades
Be authentic, lead with
humility, and recognize the
needs of others. Care for one
another and extend a helping
hand wherever it’s needed.
Honor our history.
Owner Progress Report | 250120 December 2025 Miron Construction Co., Inc. | 5
Sources
- revize: Report (3hLTHJ2MqwS4Ba7UZK4nO46c2ZypMU.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - 250120 Tiffin Recreation Center Monthly Report - December 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-4 Tiffin Recreation Center - Project Update
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.