Tiffin Recreation Center - Project Update

Open the PDF

Page 5 of 19

Text from the PDF text layer; check the PDF for anything that matters.
Executive Summary Overview Happy New Year and welcome to the project completion year! The pre-engineered building installers have been busy! The skeleton of the building is completed. They are getting the building ready for siding by installing jambs were the horizontal siding will go and installing strapping on the underside of the roof. Metal panels on the North have started and will continue wrapping around the building. The masons are wrapping up the locker rooms and working well with the plumber and electrician to make sure in wall rough-in’s are completed. The steel beams, that the track hangs from are installed as well. Looking ahead in January, the roof and siding will continue. We will also start steel erection for the 2nd floor. Major Milestones / Accomplishments • Pre-engineered building erected • Exterior metal siding has started Upcoming Milestones • Building enclosure Key Issues and Concerns • Color selection of AF-2 • Electrical and Gas service to building • Weather and building enclosure to pour slabs on grades Be authentic, lead with humility, and recognize the needs of others. Care for one another and extend a helping hand wherever it’s needed. Honor our history. Owner Progress Report | 250120 December 2025 Miron Construction Co., Inc. | 5

Sources

  • revize: Report (3hLTHJ2MqwS4Ba7UZK4nO46c2ZypMU.pdf) — where it was found ↗ first seen Oct 12, 2026
  • sharepoint (L-4 - 250120 Tiffin Recreation Center Monthly Report - December 2025.pdf) — where it was found ↗ first seen Oct 12, 2026

Attached to agenda item: L-4 Tiffin Recreation Center - Project Update

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.