Tiffin Recreation Center - Project Update

Open the PDF

Page 18 of 19

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin Community Recreation Center Layout Name: 250120B Construction Schedule Update 1/09/2026 Miron Construction Co., Inc. Data Date: 09-Jan-26 Page 4 of 4 250120-31PM 20260109 Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026 Dur Dur Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov 1650 CEILING 1640 1820 1st Floor Ceiling Tile - Drop 2 2 07-Jul-26 08-Jul-26 2090 ILTENS 3080, 1720, HVAC Startup 3 3 07-Jul-26 09-Jul-26 1640, 1820, 1730 PHILLIPSFLR 1700, 1620, 1810, 1760 Flooring - Turf Area 10 10 10-Jul-26 23-Jul-26 2090 1740 APPLEBY 1630, 2080, Soft Goods Flooring - 1st Floor 10 10 10-Jul-26 23-Jul-26 1830, 2920 1810 PHILLIPSFLR 2090 2090 1760 Athletic Flooring - 2nd Floor 15 15 10-Jul-26 30-Jul-26 2080 GENTRADES 3100, 1760 Architectural Casework Install 15 15 10-Jul-26 30-Jul-26 1620, 2860 PHILLIPSFLR 1680, 2090 1720 Athletic Flooring - 1st Floor 10 10 10-Jul-26 23-Jul-26 1720 H2I 1970, 1820, Wood Flooring - Gym Area 30 30 24-Jul-26 04-Sep-26 1620, 1950 2920 MIRON DOOR 2090, 1740, 1820 Interior Door and Harware Installation 5 5 24-Jul-26 30-Jul-26 2990, 1820 MEP 3000 1720, 1760, Test & Balance 9 9 07-Sep-26 17-Sep-26 1650, 1880 1880 MEP 2090, 1820 1760 Commissioning 9 9 18-Sep-26 30-Sep-26 WEATHER CONTINGENCY 202 202 12-Jan-26 23-Oct-26 WEATHER CONTINGENCY SITE WORK BP1 4 4 12-Jan-26 15-Jan-26 1750 MIRON 2040 Weather Contingency Sitework (May '25-July'25 6 Days) 4 4 12-Jan-26 15-Jan-26 CRITICAL 0 0 NON-CRITICAL 0 0 WEATHER CONTINGENCY CONSTRUCTION BP2 7 7 15-Oct-26 23-Oct-26 1890 MIRON 1770 1780 Weather Contingency Construction (Sept '25-Jan '26 12 Days) 7 7 15-Oct-26 23-Oct-26 CRITICAL 0 0 NON-CRITICAL 0 0 CONSTRUCTION BULLETINS 0 0 PROJECT COMPLETION 31 31 21-Sep-26 02-Nov-26 1760 MIRON 1820, 1770 Quality Control Review 10 10 21-Sep-26 02-Oct-26 1870, 1770 MIRON 1880, 1760 1890, Punchlist 8 8 05-Oct-26 14-Oct-26 1780 1780 MIRON 1890, 1790 Substantial Completion 0 0 26-Oct-26* 1770 1790 MIRON 1780 1800 Punchlist Corrections 5 5 27-Oct-26 02-Nov-26 1800 MIRON 1790 Final Completion 0 0 02-Nov-26 Actual Work Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.

Sources

  • revize: Report (3hLTHJ2MqwS4Ba7UZK4nO46c2ZypMU.pdf) — where it was found ↗ first seen Oct 12, 2026
  • sharepoint (L-4 - 250120 Tiffin Recreation Center Monthly Report - December 2025.pdf) — where it was found ↗ first seen Oct 12, 2026

Attached to agenda item: L-4 Tiffin Recreation Center - Project Update

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.