Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 1/09/2026
Miron Construction Co., Inc. Data Date: 09-Jan-26
Page 2 of 4
250120-31PM 20260109
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
3120 MERIT 3190, 3130, Roofing Building B 4 3 08-Jan-26 A 19-Jan-26
3090 2780
1450 MERIT 1370, 1390, Roofing Building A 15 15 12-Jan-26 30-Jan-26
2370 2780
2520 ZEPHYR 3110, 2510 Curtain Wall/Aluminum Entrance/Glazing - Field Verification 1 1 12-Jan-26* 12-Jan-26
3090,
2850 ILTENS 1370
1590, 2430 RTU Setting 2 2 19-Jan-26 20-Jan-26
1690
2380 TSF 2300, 2440 Steel - Sequence 4 Columns/Beams 8 8 20-Jan-26 29-Jan-26
2000,
3130 MERIT 1370,
3120, 3200 Roofing Building C 6 6 20-Jan-26 27-Jan-26
3110
3200 MERIT 3130, 2780 Exterior Metal Panels Building C 2 2 28-Jan-26 29-Jan-26
3110
2440 TSF 2380 2450 Steel - Sequence 4 Joist/Detailing 10 10 30-Jan-26 12-Feb-26
2460 TSF 2390 2470 Steel - Sequence 5 Beams/Channels 9 9 02-Feb-26 12-Feb-26
2110 AAAMECH 1440 1990 Plumbing Inwall Rough In - Exterior PEMB Walls 10 10 05-Feb-26 18-Feb-26
2470 TSF 2460 2480 Steel - Sequence 5 Detailing 4 4 05-Feb-26 10-Feb-26
2780 GENTRADES 3200, 1430, Temp Heat 10 10 05-Feb-26 18-Feb-26
1450, 1390
3140 PRICEELEC 1440,
1440 1990 Electrical Inwall Rough In - Exterior PEMB Walls 10 10 05-Feb-26 18-Feb-26
2450 TSF 2440 2390, Steel - Sequence 4 Metal Decking 4 4 06-Feb-26 11-Feb-26
1430
2480 TSF 2470 2400, Steel - Sequence 5 Decking 4 4 11-Feb-26 16-Feb-26
2950
2390 TSF 2310, 2460 Steel - Sequence 5 Track Rods 2 2 12-Feb-26 13-Feb-26
2450,
1430 MIRON CONC 2370
2450, 1550, Prep/Pour/Strip 2nd Floor to GL 5 5 5 19-Feb-26 25-Feb-26
2780 1570,
2400 TSF 2480, 1840,
2410 Steel - Sequence 6 Main Stair Install/Detail 5 5 19-Feb-26 25-Feb-26
2320
1410 MIRON 1390 Preinstall - Gym Floor and Slab on Grade 0 0 26-Feb-26
2950 MIRON CONC 1430, 1980 Prep/Pour/Strip 2nd Floor Sequence 2A 3 3 26-Feb-26 02-Mar-26
2480
1980 MIRON CONC 2950 1390, Prep/Pour/Strip 2nd Floor Sequence 2B 2 2 03-Mar-26 04-Mar-26
2930
1390 MIRON CONC 1450, 1970, Prep/Pour/Strip Slab on Grade - Gym Floor (Orange) 5 5 05-Mar-26 11-Mar-26
2780, 1360,
1570 AAAMECH 1980,
1430 1580,
1560, 2nd Floor Overhead Rough In - MEP 8 8 05-Mar-26 16-Mar-26
1580
2930 TRI CITY FP 1980 1680 2nd Floor Fire Protection 15 15 05-Mar-26 25-Mar-26
1970 MIRON 1390 1720 Gym Floor Moisture Mitigation 40 40 12-Mar-26 06-May-26
2430 TSF 2850, 1960 Steel - Sequence 9 Mechanical Screens Install 15 15 12-Mar-26 01-Apr-26
2350
1360 MIRON CONC 1390 2840, Prep/Pour/Strip Slab on Grade - Pink 3 3 12-Mar-26 16-Mar-26
1520,
3170 PRICEELEC 1390 1540
1680 Gym Area Overhead Rough In - Electrical 15 15 12-Mar-26 01-Apr-26
3180 ILTENS 1390 1680 Gym Area Overhead Rough In - Mechanical 10 10 12-Mar-26 25-Mar-26
1550 PEARSON 1430, 2340, 2nd Floor Interior Steel Stud Framing 5 5 16-Mar-26 20-Mar-26
2980 1560,
1840 GLAZING 1430, 3160
1600, Glazing 15 15 16-Mar-26 03-Apr-26
2510, 1940
1580 AAAMECH 2530
1570, 1680 Gym Area Overhead Rough In - Plumbing 5 5 17-Mar-26 23-Mar-26
1390
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Report (3hLTHJ2MqwS4Ba7UZK4nO46c2ZypMU.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - 250120 Tiffin Recreation Center Monthly Report - December 2025.pdf) — where it was found ↗ first seen Oct 12, 2026