Tiffin Recreation Center - Project Update
Page 11 of 19
Text from the PDF text layer; check the PDF for anything that matters.Progress Photos
Last PEMB beam for the court area Continuation of roof purlins
Start of North section PEMB Start of West section PEMB
Mason’s preparing for East locker room East locker room CMU wall starting
wall
Owner Progress Report | 250120 December 2025 Miron Construction Co., Inc. | 11