contract agreement · K-2
Discussion and Consideration of Pay Application #8 – Miron Construction, Recreation Center – Motion to Approve
Page 8 of 56
Text from the PDF text layer; check the PDF for anything that matters.Application and Certificate For Payment -- page 3
To Owner: Miron Constuction INC Application No: 4 Date: 12/12/25 Period To: 12/31/25
From (Contractor): Price Electric Contractor's Job Number: CA-250877
Project: Tiffin Rec Center BP2 Architect's Project No:
Work Completed
Materials Completed and
Item Scheduled Previous Presently Stored Stored to Date Balance to Finish
Number Description Value Application This Period % Retention Memo
710 Mobilization 10,000.00 10,000.00 0.00 0.00 10,000.00 100.00 0.00 300.00
900 Rental 10,000.00 3,000.00 1,000.00 0.00 4,000.00 40.00 6,000.00 120.00
901 Submittals 5,000.00 2,500.00 2,500.00 0.00 5,000.00 100.00 0.00 150.00
RFC-001 ASI-02 Transformer Pad 2,751.89 2,751.89 0.00 0.00 2,751.89 100.00 0.00 82.56
RFC-002 Deduct to change to MC cable -7,358.01 -7,358.01 0.00 0.00 -7,358.01 100.00 0.00 -220.74
Application Total 673,333.88 76,163.88 49,229.00 158,750.00 284,142.88 42.20 389,191.00 8,524.29
Sources
- revize: Attachment (ktduT2qpzI0EPfMOWwndVUEDGxi4LF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-2 - Pay Application 8 - Miron Construction - Recreation Center.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #8 – Miron Construction, Recreation...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.