Text from the PDF text layer; check the PDF for anything that matters. Miron Construction Co., Inc.
CONTINUATION SHEET AIA DOCUMENT G703
Page: 4
AIA DOCUMENT G702, APPLICATION AND CERTIFICATE FOR PAYMENT, containing
Contractor's signed Certification is attached. APPLICATION NUMBER: 8
In tabulation below, amounts are stated to the nearest cent. APPLICATION DATE: 01/05/2026 INVOICE NO.:
Use Column I on Contracts where variable retainage for line items may apply. PERIOD TO: 12/31/2025 250120-0008
PROJECT NO: 250120
A B C D E F G H I
SCHEDULED VALUE WORK COMPLETED (D+E)
TOTAL
MATERIAL
FROM COMPLETED PER- BALANCE
ITEM NO. DESCRIPTION OF WORK CHANGE PRESENTLY RETAINAGE
ORIGINAL CURRENT PREVIOUS THIS PERIOD AND STORED %(GIc TO FINISH
ORDERS STORED
APPLICATION TO DATE
215 Landscaping Allowance 75,000.00 -75,000.00 0.00 0.00 0.00 0.00 0.00 0 0.0( 0.00
220 Unreleased Add #3 Allowance 10,000.00 -10,000.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00
Project Total 12,435,142.001 -1,042,001.88 11,393,140.12 3,082,542.471 724,185.62 173,400.00\ 3,980, 128.09\ 35 7,413,012.03 199,006.41
AIA DOCUMENT G703 - APPLICATION AND CERTIFICATE FOR PAYMENT
THE AMERICAN INSTITUTE OF ARCHITECTS 1735 NEW YORK AVENUE NW WASHINGTON DC 20006
Sources
- revize: Attachment (ktduT2qpzI0EPfMOWwndVUEDGxi4LF.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-2 - Pay Application 8 - Miron Construction - Recreation Center.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #8 – Miron Construction, Recreation...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.