Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>Application No.: 2</th>
<th>Application Period:</th>
<th>From</th>
<th>08/01/25</th>
<th>to</th>
<th>09/30/25</th>
<th>Application Date:</th>
<th>09/26/25</th>
</tr>
<tr>
<td>25</td>
<td>Rebar - Labor</td>
<td>$71,872.60</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>71,872.60</td>
</tr>
<tr>
<td>26</td>
<td>Base Footings Materials</td>
<td>$89,665.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>89,665.00</td>
</tr>
<tr>
<td>27</td>
<td>Base Footings Labor</td>
<td>$49,315.75</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>49,315.75</td>
</tr>
<tr>
<td>28</td>
<td>Wall Footings Materials</td>
<td>$98,663.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>98,663.00</td>
</tr>
<tr>
<td>29</td>
<td>Wall Footings Labor</td>
<td>$54,264.65</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>54,264.65</td>
</tr>
<tr>
<td>30</td>
<td>Floor Slab Materials</td>
<td>$156,442.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>156,442.00</td>
</tr>
<tr>
<td>31</td>
<td>Floor Slab Labor</td>
<td>$88,874.50</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>88,874.50</td>
</tr>
<tr>
<td>32</td>
<td>Equipment Pads Materials</td>
<td>$1,515.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>1,515.00</td>
</tr>
<tr>
<td>33</td>
<td>Equipment Pads Labor</td>
<td>$3,451.50</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>3,451.50</td>
</tr>
<tr>
<td>34</td>
<td>Precast Concrete Materials</td>
<td>$575,000.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>575,000.00</td>
</tr>
<tr>
<td>35</td>
<td>Precast Concrete Labor</td>
<td>$204,412.67</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>204,412.67</td>
</tr>
<tr>
<td>36</td>
<td>Structure 30- Clearwell</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>37</td>
<td>Rebar Materials</td>
<td>$204,551.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>204,551.00</td>
</tr>
<tr>
<td>38</td>
<td>Rebar labor</td>
<td>$112,503.05</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>112,503.05</td>
</tr>
<tr>
<td>39</td>
<td>Mat Foundation - Materials</td>
<td>$123,255.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>123,255.00</td>
</tr>
<tr>
<td>40</td>
<td>Mat Foundation - Labor</td>
<td>$68,450.80</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>68,450.80</td>
</tr>
<tr>
<td>41</td>
<td>Walls - Materials</td>
<td>$78,452.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>78,452.00</td>
</tr>
<tr>
<td>42</td>
<td>Walls - Labor</td>
<td>$98,065.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>98,065.00</td>
</tr>
<tr>
<td>43</td>
<td>Elevated Slab - Materials</td>
<td>$198,553.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>198,553.00</td>
</tr>
<tr>
<td>44</td>
<td>Elevated Slab - Labor</td>
<td>$109,204.15</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>109,204.15</td>
</tr>
<tr>
<td>45</td>
<td>Precast Concrete - Materials</td>
<td>$210,000.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>210,000.00</td>
</tr>
<tr>
<td>46</td>
<td>Precast Concrete - Labor</td>
<td>$61,058.33</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>61,058.33</td>
</tr>
<tr>
<td>47</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>48</td>
<td>Masonry</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>49</td>
<td>Masonry - Materials</td>
<td>$15,116.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>15,116.00</td>
</tr>
<tr>
<td>50</td>
<td>Masonry - Labor</td>
<td>$50,603.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>50,603.00</td>
</tr>
<tr>
<td>51</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>52</td>
<td>Metals</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>53</td>
<td>Metal Fabrications - Materials</td>
<td>$57,200.00</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>57,200.00</td>
</tr>
<tr>
<td>54</td>
<td>Metal Fabrications - Labor</td>
<td>$13,556.25</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>13,556.25</td>
</tr>
<tr>
<td>55</td>
<td>Handrails & Railings Labor</td>
<td>$5,966.50</td>
<td>-</td>
<td>-</td>
<td>-</td>
<td>0%</td>
<td>5,966.50</td>
</tr>
</table>
Sheets in this document
- p. 19 A.200 · South Elevation
- p. 20 Floor Plan
- p. 21 Floor Plan · Basement
- p. 22 A.200 · South Elevation
- p. 23 A.201 · North Elevation
- p. 24 Floor Plan · Level 2
- p. 25 A.200 · Building Elevations
- p. 26 Floor Plan · Level 2
- p. 27 C200 · Site Layout · Iowa DOT
- p. 28 C300 · Site Utilities Plan
- p. 29 C301 · Site Utilities South
- p. 30 Revised Site Plan
- p. 31 Preliminary Plat
- p. 32 2 · Road Typical Section
- p. 33 3 · Address City Comments Revised Phasing & Utility Layout
- p. 43 H2 · MSA
- p. 44 H3 · MSA
- p. 45 H4 · MSA
- p. 51 Acquisition Plat · Iowa DOT · Reeve'S Addition Part One
- p. 52 YW25 · Acquisition Plat · Iowa DOT
- p. 53 Acquisition Plat · Iowa DOT
- p. 54 Acquisition Plat · Iowa DOT
- p. 55 Section: 28 · Iowa DOT
- p. 56 Plot Plan · Iowa DOT
- p. 57 Plot Plan · Iowa DOT
- p. 62 Acquisition Plat · Iowa DOT · Reeve'S Addition Part One
- p. 63 Acquisition Plat · Iowa DOT · US Highway 6 Reconstruction
- p. 64 Acquisition Plat · Iowa DOT
- p. 65 Acquisition Plat · Iowa DOT · US Highway 6 Reconstruction
- p. 66 Acquisition Plat · Iowa DOT · US Highway 6 Reconstruction Tiffin, Iowa
- p. 119 MSA · Water Treatment Plant Upgrades - City of Tiffin
Sources
- revize: Agenda packet (packet_2026-02-03_01b8a8d6-6f0a-495e-b8d2-c37c2999a723.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 20, 2026. Built from the archive's documents; see how the data is built.