Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: | MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Application No.: 1 Application Period: From 04/22/25 to 07/30/25 Application Date: 07/22/25
25 Rebar - Labor $71,872.60 - 0% 71,872.60
26 Base Footings Materials $89,665.00 - 0% 89,665.00
27 Base Footings Labor $49,315.75 - 0% 49,315.75
28 Wall Footings Materials $98,663.00 - 0% 98,663.00
29 Wall Footings Labor $54,264.65 - 0% 54,264.65
30 Floor Slab Materials $156,442.00 - 0% 156,442.00
31 Floor Slab Labor $88,874.50 - 0% 88,874.50
32 Equipment Pads Materials $1,515.00 - 0% 1,515.00
33 Equipment Pads Labor $3,451.50 - 0% 3,451.50
34 Precast Concrete Materials $575,000.00 - 0% 575,000.00
35 Precast Concrete Labor $204,412.67 - 0% 204,412.67
- -
36 Structure 30- Clearwell
37 Rebar Materials $204,551.00 - 0% 204,551.00
38 Rebar labor $112,503.05 - 0% 112,503.05
39 Mat Foundation - Materials $123,255.00 7 0% 123,255.00
40 Mat Foundation - Labor $68,450.80 - 0% 68,450.80
Al Walls - Materials $78,452.00 - 0% 78,452.00
42 Walls - Labor $98,065.00 - 0% 98,065.00
43 Elevated Slab - Materials $198,553.00 - 0% 198,553.00
44 Elevated Slab - Labor $109,204.15 - 0% 109,204.15
45 Precast Concrete - Materials $210,000.00 - 0% 210,000.00
46 Precast Concrete - Labor $61,058.33 - 0% 61,058.33
- -
47
“ A
48 Masonry
49 Masonry - Materials $15,116.00 - 0% 15,116.00
50 Masonry - Labor $50,603.00 - 0% 50,603.00
- -
51
- -
52 Metals
53 Metal Fabrications - Materials $57,200.00 - 0% 57,200.00
54 Metal Fabrications - Labor $13,556.25 - 0% 13,556.25
55 Handrails & Railings Labor $5 966.50. - 0% 5 966.50
© National Society of Professional Engineers for EJCDC. All rights reserved.
EJCDC® C-620 Contractor's Application for Payment
00 62 76 ~ 2 of 10 TiffinWTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application
\\FILESERVER\Shares\Projects\Active\
Sources
- revize: Agenda packet (packet_2026-02-03_01b8a8d6-6f0a-495e-b8d2-c37c2999a723.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 19, 2026. Built from the archive's documents; see how the data is built.