Text read by the vision model; check the PDF for anything that matters.PAYMENT APPLICATION
DATE: December 15, 2025
PROJECT NAME: City of Tiffin Community Recreation Center
ADDRESS: Tiffin, IA
CONTRACT FOR: FI-23.00/HVAC
MIRON PROJECT: 250120 CONTRACT #: 250120-000025 VENDOR#: 00005737
REQUEST NUMBER: 2 PERIOD FROM: 12/01/2025 TO: 12/31/2025
INVOICE NUMBER: 63477 INVOICE DATE: 12/15/2025
<table>
<tr>
<th>ORIGINAL CONTRACT AMOUNT</th>
<td>$719,950.00</td>
</tr>
<tr>
<th>APPROVED CHANGE ORDERS AS OF August 21, 2025</th>
<td>0</td>
</tr>
<tr>
<th>ADJUSTED CONTRACT AMOUNT</th>
<td>719,950.00</td>
</tr>
<tr>
<th>TOTAL COMPLETED TO DATE</th>
<td>27,005.00</td>
</tr>
<tr>
<th>PREVIOUS REQUESTS FOR PAYMENT</th>
<td>9,775.00</td>
</tr>
<tr>
<th>TOTAL EARNED THIS REQUEST</th>
<td>17,230.00</td>
</tr>
<tr>
<th>LESS 5% RETAINAGE</th>
<td>861.50</td>
</tr>
<tr>
<th>CURRENT PAYMENT DUE</th>
<td>16,368.50</td>
</tr>
</table>
VENDOR: Illens Inc
SIGNED:
TITLE: President
*** REQUESTS WILL NOT BE PROCESSED UNTIL THEY ARE SUBMITTED TO MIRON VIA E-MAIL IN A PDF FORMAT TO [email protected] OR ORIGINALS ARE RECEIVED. FAX COPIES WILL NOT BE ACCEPTED.
• EACH PAYMENT APPLICATION MUST INCLUDE AN UP TO DATE SCHEDULE OF VALUES, INCLUDING SUB TIER SUPPLIER/SUBCONTRACTOR BREAKDOWN AND CURRENT PAYMENT STATUS. CHANGE ORDERS ISSUED TO DATE MUST BE REFLECTED ON THE CURRENT SCHEDULE OF VALUES.
Sheets in this document
- p. 37 1 · Lots Layout · Shoemaker & Haaland · Valley Subdivision (37-20)
- p. 38 2 · DWN: MJW Survey Date(S): 2024 · Valley Subdivision (37-20)
- p. 54 Preliminary Plat · MMS Consultants
- p. 247 Renewal Communications Flow
- p. 275 City of Tiffin FY 25-26 Town Hours by Month (chart; data on p. 274)
- p. 278 City of Tiffin FY 25-26 (chart; data on p. 276)
- p. 309 2nd Floor In Wall Rough In · Prep/Pour/Strip Slab on Grade