Text read by the vision model; check the PDF for anything that matters.SECTION 6. PHASED DEVELOPMENT
If the plat is a phase of a multi-phased preliminary plat, the City may refuse to approve final plats of subsequent phases if the Developer has breached this Agreement and the breach has not been remedied. Development of subsequent phases will not be allowed to proceed until Developer's Agreements for such phases are approved by the City.
SECTION 7. MISCELLANEOUS
A. The Developer represents and states that the plat complies with all City, state and federal laws and regulations, including but not limited to subdivision ordinances, zoning ordinances and environmental regulations. The City may, at its option, refuse to allow construction or development work in the subdivision until the Developer complies with the appropriate law or regulation. Upon the City's demand, the Developer shall cease work until there is compliance.
B. Third parties shall have no recourse against the City under this Agreement.
C. Breach of the terms of this Agreement by the Developer shall be grounds for denial of building permits, occupancy permits or other permits.
D. If any portion, section, subsection, sentence, clause, paragraph or phrase of this Agreement is for any reason held invalid, such decision shall not affect the validity of the remaining portion of this Agreement.
E. The action or inaction of the City shall not constitute a waiver or amendment to the provisions of this Agreement. To be binding, amendments or waivers must be in writing, signed by both parties and approved by written resolution of the City Council. The City's failure to promptly take legal action to enforce this Agreement shall not be a waiver or a release.
F. The Developer may not assign this Agreement or the obligations imposed by this Agreement without the written permission of the City Council or as otherwise provided in this Agreement.
G. The Developer's obligations under this Agreement shall continue in full force and effect even if the Developer sells a portion of the subdivision, the entire platted area, or any part thereof.
H. No building permits will be issued until all public improvements have been constructed in accordance with applicable standards and formally accepted by the City. No occupancy permits will be issued until all public improvements have been constructed in accordance with applicable standards and formally accepted by the City.