Text read by the vision model; check the PDF for anything that matters.RESOLUTION NO. 2015-114
RESOLUTION FOR FINAL ACCEPTANCE OF THE
2014 WATER AND SEWER EXTENSION PROJECT; DIVISION II: GRAVITY SEWER
AND FORCEMAIN – TIFFIN, IOWA
WHEREAS, On October 21, 2015 the Project Engineer states the Project construction was completed in general accordance with the approved Plans and Specifications on file with the City of Tiffin, Iowa and placed into operation and recommends Final Payment be made to the Contractor.
THEREFORE, BE IT RESOLVED, BY The City of Tiffin, Iowa, that the 2014 Water and Sewer Extension Project –is complete and acceptable to the City and final payment be made to the Contractor.
Passed and approved this 28th day of October, 2015.
AYE: Jo Kahler, Mike Ryan, Al Havens, Jim Bartels, Peggy Upton
NAY: None
ABSENT: None
SIGNED:
Steve Berner, Mayor
ATTEST:
Doug Boldt, City Clerk