Page 1 of 1
Text read by the vision model; check the PDF for anything that matters.RESOLUTION NO. 2015-062
A Resolution Approving Pay Estimate #4 from WRH, Inc for 2014 Water & Sewer Extension Project(CCA Schools) DIV III for the amount of $262,368.15
Whereas, The City received confirmation that a phase of the above project has been completed and verification has been confirmed of completion thus far by the City engineer and the contractor, WRH, Inc, has properly submitted a pay estimate for payment.
Now, therefore be it resolved by the City Council of the City of Tiffin, Iowa to approve the pay estimate #2 to WRH, Inc for the 2014 Water & Sewer Extension Project DIV III (CCA School) in the amount of $262,368.15.
On the 13th day of May, 2015, at a regular meeting of the Tiffin City Council, Tiffin, Iowa, Councilperson Ryan introduced Resolution No. 2015-062, A RESOLUTION Approving Pay Estimate #2 from Cornerstone for 2014 Water & Sewer Extension Project (CCA Schools) DIV II for the amount of $262,368.15 and made a motion for approval. Motion seconded by Councilperson Upton.
Ayes: Kahler, Ryan, Upton, Bartels, Havens.
Nays: NONE
Absent: NONE
Whereupon five Council members were present and voted approval and Mayor Berner declared that the Resolution No. 2015-062, A RESOLUTION Approving Pay Estimate #2 from WRH, Inc for 2014 Water & Sewer Extension Project(CCA Schools) DIV III for the amount of $262,368.15 to be adopted and signified his approval of the same by affixing his signature thereto.
Passed by the City Council on the 13th day of May, 2015.
City of Tiffin
[Signature]
Steven L. Berner, Mayor
ATTEST:
[Signature]
Tim Long, City Administrator/Clerk
Sources
- laserfiche: Resolutions-2015-062 (Resolutions-2015-062.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.