Text read by the vision model; check the PDF for anything that matters.RESOLUTION NO. 2015-061
A Resolution Approving Pay Estimate #4 from Cornerstone for 2014 Water & Sewer Extension Project (CCA Schools) DIV II for the amount of $241,167.88
Whereas, The City received confirmation that a phase of the above project has been completed and verification has been confirmed of completion thus far by the City engineer and the contractor, Cornerstone Excavating, has properly submitted a pay estimate for payment.
Now, therefore be it resolved by the City Council of the City of Tiffin, Iowa to approve the pay estimate #4 to Cornerstone Excavating for the 2014 Water & Sewer Extension Project DIV II (CCA School) in the amount of $241,167.88.
On the 13th day of May, 2015, at a regular meeting of the Tiffin City Council, Tiffin, Iowa, Councilperson Ryan introduced Resolution No. 2015-061, A RESOLUTION Approving Pay Estimate #4 from Cornerstone for 2014 Water & Sewer Extension Project (CCA Schools) DIV II for the amount of $241,167.88 and made a motion for approval. Motion seconded by Councilperson Kahler.
Ayes: Kahler, Ryan, Upton, Bartels, Havens.
Nays: NONE
Absent: NONE
Whereupon five Council members were present and voted approval and Mayor Berner declared that the Resolution No. 2015-061, A RESOLUTION Approving Pay Estimate #4 from Cornerstone for 2014 Water & Sewer Extension Project (CCA Schools) DIV II for the amount of $241,167.88 to be adopted and signified his approval of the same by affixing his signature thereto.
Passed by the City Council on the 13th day of May, 2015.
City of Tiffin
[Signature]
Steven L. Berner, Mayor
ATTEST:
[Signature]
Tim Long, City Administrator/Clerk