Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades- City of Tiffin
Contract:
Application No.: 6R Application Period: From 01/24/26 to 02/20/26 Application Date: 02/20/26
25 Rebar - Labor $71,872.60 21,561.78 35,936.30 57,498.08 80% 14,374.52
26 Base Footings Materials $89,665.00 89,665.00 89,665.00 100% -
27 Base Footings Labor $49,315.75 49,315.75 49,315.75 100% -
28 Wall Footings Materials $98,663.00 2 98,663.00 98,663.00 100% -
29 Wall Footings Labor $54,264.65 - 54,264.65 54,264.65 100% -
30 Floor Slab Materials $156,442.00 - - 0% 156,442.00
31 Floor Slab Labor $88,874.50 - - 0% 88,874.50
32 Equipment Pads Materials $1,515.00 - - 0% 1,515.00
33 Equipment Pads Labor $3 451.50 - - 0% 3,451.50
34 Precast Concrete Materials $575,000.00 - 12,125.00 12,125.00 2% 562,875.00
35 Precast Concrete Labor $204,412.67 - - 0% 204,412.67
36 Structure 30- Clearwell - - -
37 Rebar Materials $204,551.00 - - 0% 204,551.00
38 Rebar labor $112,503.05 - - 0% 112,503.05
39 Mat Foundation - Materials $123,255.00 - - 0% 123,255.00
40 Mat Foundation - Labor $68,450.80 - - 0% 68,450.80
Al Walls - Materials $78,452.00 - - 0% 78,452.00
42 Walls - Labor $98,065.00 - - 0% 98,065.00
43 Elevated Slab - Materials $198,553.00 - - 0% 198,553.00
44 Elevated Slab - Labor $109,204.15 = - 0% 109,204.15
45 Precast Concrete - Materials $210,000.00 - - 0% 210,000.00
46 Precast Concrete - Labor $61,058.33 - - 0% 61,058.33
47 - - -
48 Masonry - < g
49 Masonry- Materials $15,116.00 - - 0% 15,116.00
50 Masonry - Labor $50,603.00 - - 0% 50,603.00
51 - - -
52 Metals - - -
53 Metal Fabrications - Materials $57,200.00 - - 0% 57,200.00
54 Metal Fabrications - Labor $13,556.25 - - 0% 13,556.25
55 Handrails & Railings Labor $5,966.50 - - 0% 5,966.50
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76 - 2 of 10 \\FILESERVER\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application