PROJECT UPDATE
HIGHWAY 6 CONCEPT AND COST ESTIMATE – JAMES WATTERS
At the time of update, a meeting on Wednesday, February 25th took place to discuss some water main changes at
Main Street, Kimberlite Street, and the east end of the project.
In the coming weeks, MSA will be sending City public works staff a revised watermain layout for review and
comment. Final plans are progressing and adjustments will be made for any water main comments received.
***MSA needs council action on the following***
1. Decide whether to fully signalize Croell Ave (Option 4) or install only unground infrastructure and
construct offset right turn lane for NB Croell Ave traffic (Option 1). See below for context on previous
discussions with council.
MSA presented costs to Council at the November 18th meeting for the following items:
1. Fully Signalized Intersection - $400-$435k per intersection
2. Installation of underground equipment for future signalized intersection at Croell Ave =
$80-$100k
Council was split as to whether to fully signalize Croell Ave now or wait until future traffic growth
warrants signalization. It was brought up that the left turn movement onto EB US 6 would still be
present with a non-signalized option at Croell Ave and US 6 and whether public feedback would continue
to be received on the safety of this intersection without signalization.
There was also discussion from council as to whether an enhanced pedestrian crossing should be
implemented at Stephens St in the form of a High-Intensity Activated Crosswalk system (HAWK Signal).
See below image.
MSA is looking for direction on the following:
1. Pursue investigations internally and with IaDOT and suitability for HAWK Signal at Stephens St.
PROJECT UPDATE
Page 2 of 6
Sources
- revize: L.1 (zv4A3ZESw8kVg8mOlzrtFK0BS4YM97.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 City Engineer's Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.