Discussion and Consideration of Pay Application #6 – Tricon Construction Group – Water Treatment Plant Upgrades – Motion to Approve — K.4
Page 1 of 12
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-4
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: February 26, 2026
AGENDA ITEM: Discussion and Consideration of Pay Application #6 – Tricon Construction
Group – Water Treatment Plant Upgrade Project
ACTION: Approval
Background
The City of Tiffin is currently constructing significant upgrades to its Water Treatment Plant
under a contract with Tricon Construction Group. The project is being administered by MSA
Professional Services. Pay Application No. 6 represents progress payment for construction work
completed between January 24, 2026 and February 20, 2026.
MSA has reviewed and recommended approval of this pay application, and the Contractor has
certified its accuracy.
Work remains ongoing and continues to progress across structural concrete, mechanical
improvements, electrical installation, and site work elements as detailed in the lump sum
progress schedule. Progress achieved this period reflects ongoing construction across the RO
Building foundations, electrical mobilization and site materials, and several structural
components.
Recommendation
Staff recommends approval of Pay Application No. 6 from Tricon Construction Group in the
amount of $557,440.64.
ATTACHMENTS: Pay Application
1
Sources
- revize: K.4 (4z0jnrGuZmCGY7AfNOCi5OY0WmX1Ea.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Pay Application #6 – Tricon Construction Group – Water...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.