Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
April 2, 2026
PROJECT UPDATE
DEVELOPMENT ASSISTANCE – ANDREW INHELDER
NO FURTHER COMMENTS
Development Name Description Date of last interaction
Park Place City Center, Part 1, Lot 3 No further comments 1/29/25
Hunt Club Phase 4 No further comments 4/9/25
Veritas Church Expansion – Phase 2 No further comments 5/15/25
Park Place City Center, Part 4, Phase
No further comments 6/24/25
4, Lot 22 – Firing Pin
Prairie Village Part 3, Phase 4 No further comments 7/11/25
301 Main Street Site Plan No further comments 8/8/25
Park Place City Center, Part 2, Phase
No further comments 2/27/26
6, Lot 33 – Multipurpose Building
Prairie Village Lot 55 – Medical Clinic No further comments 1/15/26
Park Place City Center, Part 1, Phase
No further comments 1/29/26
4, Lot 1 OPD – Event Center
Phase 1 is completed (reroute storm coming from I-
380).
Homemaker’s Site Plan – Phase 1 & 2 Ongoing
Phase 2 has no further comments. (Onsite
Improvements)
Dollar General No further comments. 3/3/26
Clear Creek Village No further comments. 3/3/26
UNDER CONSTRUCTION
Development Name Description Date of last interaction
Punchlist walkthrough performed. Contractor to
Tiffin West Phase 1B 9/24/25
complete punchlist and notify MSA of completion.
Walkthrough performed. Contractor to complete
Tiffin Heights West ON Site 10/24/25
punchlist and notify MSA of completion.
Currently under construction.
Village Drive Extension (By water Construction began in May 2025.
4/2/26
tower) Project walkthrough was completed and several
punchlist items were identified.
Currently under construction.
The States – Anderson Addition OPD Ongoing
Construction began May 2025.
Currently under construction.
Bailey Way Extension
Construction began October 2025. Ongoing
Awaiting resubmission on Easement exhibit.
Currently under construction.
Homemaker’s Site Plan – Phase 2 Ongoing
Construction began February 2026.
Grove Park Currently under construction. 2/4/26
PROJECT UPDATE
Page 4 of 6
Sources
- revize: L.1 (qbSs9LxUFCc343YmzNOV7epOV9o1z5.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 Engineer's Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.